Excavation of the station has reached the formation level and casting of the underplatform/platform level are in progress. Excavation and RC works are simultaneously taking place across the entrances. TBM 1 has completed the second drive to Upper Thomson Station last month and dismantling works are in progress.
| Completed concourse slab towards entrance D. Internal RC wall works for south TVF/VS/VE in progress. |
| Service opening site behind entrance D |
| Entrance C site |
| RC works for cooling tower structure over entrance C |
| RC works at the base slab of the station |
| Entrance A |
| Pipe jacking shaft backfilled at entrance B |
| Excavation of entrance B |
![]() |
| Tunnel Chart for TEL1, December 2017 |