RC works progresses at the station's concourse level. Structure around entrance B has surfaced to the basement roof level with formwork installation ongoing in preparation for the first roof slab cast.
| Mount Pleasant Station |
| Entrance B |
| RC works for concourse to roof slab structure. Formwork installation ongoing for the roof slab around the entrance. |
| Concourse unpaid & paid area boundary (south end) |
| Station area (north end) |
| Opening in concourse slab down to the mezzanine & platform levels. The escalator landing pits for escalator 5 and 6 between the concourse and mezzanine levels are carved out in the concourse slab |
| RC wall works for service rooms at the north end |
| Entrance A |
| Tunnelling works for the second drive set to complete within the next few weeks. |