Friday 21 April 2017

Gardens By The Bay Cast (II)

Casting of the permanent structure at the station is progressing at varying levels, with portions of the platform and tunnel walls along both bounds completed. The second phase of traffic realignment, to be implemented next month, will see Marina Gardens Drive reduced to a single lane dual carriageway.


Gardens By The Bay station site

Thursday 20 April 2017

Marina South Cast (II)

Casting of the station has reached the concourse level, while portions of the C&C tunnel roof have been completed.


Overview of the T227 open cut excavation site with T228 & T302 in the background

Wednesday 19 April 2017

Marina Bay Excavation (IV)

Excavation works have presumably reached the upper platform level and is progressing down to the lower platform.


Commencement of shoring and excavation works at Entrance B

Tuesday 18 April 2017

Shenton Way Cast (III)

Excavation works have reached the plantroom level and is progressing down to the upper platform level. Assembly of TBM 1 has completed and commencement of tunnelling works to Maxwell are slated to begin tomorrow.


Concourse slab completed at the station

Monday 17 April 2017

Maxwell Cast

Bulk excavation and casting work continues at the Maxwell station.


Roof slab completed at zone 3 (bottom)

Sunday 16 April 2017

Outram Park Excavation (II)

The concourse slab has been cast and excavation works for the station are now at the platform level of the station. The final realignment of Outram Road was carried out last month for the excavation of the new interchange linkways, and would remain in position till the end of the project. TBM2 has almost completed the Changi bound tunnel towards Maxwell.


TBM 1 re-assembly works at launch shaft towards Havelock

Saturday 15 April 2017

Thursday 13 April 2017

Great World Excavation (II)

The concourse slab for the station has been completed and excavation works are now progressing down to the platform level. Bored tunnel works are underway in both directions towards Orchard and Havelock stations.


Excavation works proceeding down to the platform level

Wednesday 12 April 2017

Tuesday 11 April 2017

Orchard Boulevard Cast (III)

Excavation works have reached the lower concourse level and casting of the structure is progressing. Excavation and casting of the platform and underplatform levels will be carried out through the year. Excavation works for the mining shaft for the underpass leading to entrance B have commenced at the facade of Camden Medical Centre along Grange Road.


Overview of T218 site