Tuesday, 20 June 2017

Tagore Backfill

Filling works are in progress over the completed structure at Tagore which would site the 1 hectare trackworks staging ground to come. The final TBM C2 is about 75% completed and will complete by the next quarter.


Backfilling works and de-strutting over the concourse slab 

Springleaf Cast (II)

Structure of the Springleaf station is taking shape with the first section of roof slab completed.


Springleaf station

Sunday, 18 June 2017

Facility Building Cast (III)

The full face rock conditions experienced by the final 2 EPBMs from Springleaf have significantly hindered the progress over the last quarter with an average advancement rate of a single ring building per day. TBM 1 is about 30 rings from breakthrough and should complete within a month's time.


Tower crane erected to facilitate the RC works of the facility building superstructure