Lentor Station achieved the BSC at the beginning of the year, with fit-out and painting works commencing. Structural works continue at the entrances. Dismantling of the TBMs have completed, and the first stage concrete & tunnel bracket installation works are ongoing between 5XO and Mayflower.
| 5XO site |
| Backfilling works over the Changi bound tunnel |
| Plan view |
| Backfilling works at Lentor Station |
| Entrance A |
| Entrance B |
| Backfilling works at temporary access |
| Entrance C |
| Backfilling works at access |
| Construction of permanent structure within launch shaft |
| Entrance D |
| Entrance E |