Casting of the base slab is progressing at the station box. The base slab is completed at Entrance C, and excavation of the adjacent subway has started. Initial drive of the TBM is presumably completed.
Gardens By The Bay Station |
Excavation works at the concourse level at GL10-15 |
Installation of gantry cranes for top-down construction of the station |
Maxwell Station |
Commencement of excavation works for the station box |
Unveiling of EPBM S-945 and delivery of counterweights for heavy lifting mobilization |
Bulk excavation works in full swing at the cut and cover tunnel |
Napier Station |
Roof slab completed over the center zone for the upcoming Stage 3A traffic diversion |
Basement roof slab completed at Entrance D |
Tagore C&C tunnel |
Dismantled gantry crane, backfilling and RC works for the facility building |
Structure for the stabling yard, bus parking deck and perimeter wall mostly completed |
Casting ongoing at the south crossover tunnel |
TEL1/2 Tunnel Chart, November 2016 |
T202 - Breakthrough of TBM 2 at Woodlands Station on October 10. This is the first contract to complete all bored tunnel excavation |
TEL 1/2 Tunnel Chart, September 2016 |
Tandem lifting of tail shield |
Completed roof slab at Orchard station |
Telescopic excavator deployed for the excavation of the south entrance |
Completion of canal diversion and demolishment of former canal in progress |
Realignment of Sin Ming Avenue (west bound carriageway) for final stretch of SBP works |
Excavation for the RC construction of the basement roof slab |
TBM B and TBM C2 progress as of September 8 |
TBM 3 and TBM 4 progress from Sembawang Airbase to RTS Facility Building |
TBM 1 and TBM 2 progress from Springleaf Station to RTS Facility Building |
RTS Facility Building |