| Casting of the station base slab in December (Photo: LTA) |
Showing posts with label TE12 - Napier. Show all posts
Showing posts with label TE12 - Napier. Show all posts
Friday, 30 March 2018
Napier Cast
The bottom-up structural works have commenced at the Napier station.
Saturday, 16 December 2017
Napier Excavation (IV)
Excavation works are nearly completed at the site. RC works have started at entrance A.
| Napier Station |
Wednesday, 27 September 2017
Napier Excavation (III)
The relaunch of TBM S-930 at the Napier launch shaft for the Changi bound tunnel drive towards Orchard Boulevard took place earlier this month on September 15. Excavation works are at the S6 layer at the deepest point and RC works for the station's underplatform structure should start by the end of the year.
| T217 Napier Station (View towards Tanglin) |
Friday, 7 July 2017
Napier Excavation (II)
Saturday, 25 March 2017
Napier Excavation
Bored pile works have completed at the station and excavation works progresses.
| Excavation works at station |
Tuesday, 20 December 2016
Piling at Napier (VII)
The final stage of piling works are scheduled to complete by the end of the year. The Herrenknecht TBM has remarkably driven the 750m long mixed-ground tunnel within just 3 months from the transition to its main drive, averaging close to 6 rings a day with interventions. The TBM is slated to reach the T218 boundary by the end of the week. Excavation works at the south side of the station box are in progress.
| Napier Station |
Tuesday, 20 September 2016
Piling at Napier (VI)
Piling works continue at the station box and is set to complete by year end upon 2 more traffic realignments along Cluny Road. Excavation works have just commenced at the south entrance. TBM S-930 has transitioned to its main drive and will continue advancement to the Orchard Boulevard Station.
| Telescopic excavator deployed for the excavation of the south entrance |
Thursday, 16 June 2016
Napier Diverts (II)
The final portion of the secant bored pile works are underway at the Napier station following the diversion of the city-bound carriageway along Holland and Napier Road. Tunnelling works has also commenced on the Woodlands bound tunnel to Orchard Boulevard.
| 3rd traffic diversion implemented at the Napier station |
Thursday, 7 April 2016
Saturday, 6 February 2016
S-930 Assembly
Assembly works for the Herrenkencht TBM have commenced at the Napier launch shaft with the both shields lowered down over the last past 2 days. Dual drives will be performed by the TBM for the twin tunnels to Orchard Boulevard, with the lower Woodlands bound tunnel to commence first by the end of this quarter.
![]() |
| Cutterhead and assembly of the heavy-lifting Terex crane in the background |
Wednesday, 23 December 2015
Piling at Napier (IV)
The second traffic diversion has taken place last month. The junction with Cluny Road has been shifted towards Gleneagles Hospital for the secant bored pile works beneath the former road. The third traffic diversion, which should be prepared by the next quarter, will see the major realignment of the city-bound carriageway along the S-bend.
The launch shaft has completed excavation works and the base slab has been cast.
Tuesday, 29 September 2015
Piling at Napier (III)
Piling works continues along the center perimeter of the Napier station following the traffic diversion in July. Excavation of the launch shaft is ongoing.
| Excavation of the launch shaft |
Saturday, 25 July 2015
Napier Diverts
The first traffic diversion at the Napier site was implemented earlier this morning. One of the major TD along the Thomson Line project, the westbound carriageway has swung away from Gleneagles and now runs alongside the launch shaft.
Photos were taken in the week leading up to the diversion.
![]() |
| July 25 - Diversion of westbound Napier and Holland road |
Tuesday, 14 July 2015
Napier - Preparations to Divert (II)
Preparation works continue for the traffic diversion works at Napier. The diversion works are taking a significant amount of time to prepare due to the complexity in the geological and utility network at the site. The curbs of the new road are now being constructed, along with the demolishment of the center median. The diversion is expected to be implemented by the end of this month.
Herrenknecht has completed assembly of the STP back in Q2. Excavation of the launch shaft is now halfway completed we can expect tunnelling to commence around year end. The gantry crane was assembled at the end of May and the delivery of the TBM should take place by Q3.
![]() |
Wednesday, 1 April 2015
Napier - Preparations to Divert
Canal diversion works have been on going at the Napier site for the past 2 months. The realigned canal will be rerouted towards the south, away from the Singapore Botanic Gardens. Preparatory work for the first traffic diversion - which will run parallel to the realigned canal, have also commenced and should be implemented by the end of this quarter. Piling works continue on Gleneagles side.
It is noteworthy that the TBM from the unrelated SPPA EW2 transmission cable tunnel project has reached the west end of the T217 site and will spend the next month or 2 tunnelling down Holland/Napier Road, perpendicularly beneath the proposed Napier station box. This is one of 3 sites whereby the TEL & cable tunnel project boundaries interface - the other 2 being Upper Thomson and Springleaf.
![]() |
| March 30 - Canal Diversion to the right of the picture which cuts into a portion of the launch shaft outline |
Monday, 12 January 2015
Piling at Napier (II)
Piling works continue at the T217 Napier site. The Gleneagles Pedestrian Overhead Bridge (POB) officially closed on Christmas Eve last year, and was successfully demolished on the morning of January 9. This is the second pedestrian overhead bridge to be demolished for the Thomson Line project. Concurrent with the former bridge's demolishment is the opening of the new temporary POB.
The site area will begin to change drastically in the coming few months. 5 stages of traffic diversions have been mapped out with the first realignment scheduled to be implemented around March or April.
Under T217, Yongnam will supply and facilitate shoring related works. In addition, Herrenknecht will be manufacturing a slurry TBM and STP for the dual tunnel drives to Orchard Boulevard station.
![]() |
| Dec 30 - Piling works towards the south |
![]() |
| Dec 30 - Dismantling of Gleneagles POB |
![]() |
| Dec 30 - Dismantling of Gleneagles POB |
Tuesday, 9 December 2014
POB Progresses @ Napier
Following the successful beam launching works back in October, works to finish up the temporary POB have proceeded on with the completion of the bridge's roof as well as the staircase along the town-bound road. The bus stop at Gleneagles was relocated last month as well. The staircase on the opposite side near the US embassy is still being constructed.
Piling works continues to go on at the launch shaft and exit. 12m high hoardings are also being erected in front of Gleneagles where the former bus bay locates.
![]() |
| Progress of the temporary steel POB |
![]() |
| Former bus bay has been demolished at Gleneagles where the 12m high noise barriers are being installed |
![]() |
| Piling works continue at the launch shaft |
Thursday, 16 October 2014
POB Launches @ Napier
The temporary Pedestrian Overhead Bridge is successfully up at Napier Road following 2 nights of beam launching. The segment over the carriageway bound for Orchard was first launched up on Tuesday morning. The second segment of steel was then launched earlier this morning over the westbound road. The temporary bus bay and shelter along the eastbound road is almost completed, and would open anytime soon.
M&E works to the temporary bridge would take place together with the construction of the bridge's staircase from now. The new temporary bridge could possibly be operational by year end, following which the existing bridge would be demolished. This is the second POB to be demolished along the line.
![]() |
| Completion of beam launching along Napier Road this morning |
The photos below show the progress of the beam launching throughout the week.
Thursday, 25 September 2014
Piling at Napier
Piling works have commenced for the launch shaft at Napier. The rigs and cranes at this site will be fitted with acoustic enclosures due to the sensitivity of noise from the surrounding developments. The bus stop opposite Gleneagles Hospital has been temporary relocated further east on Sep 14. A new bus bay can also be seen along the Eastbound road. The 2 bus bays are adjacent to each other along both sides of the road, and will be linked by a temporary POB. We can expect the new bridge to come up by year end.
Once the old bridge has been demolished, a staged traffic diversion would begin to take place.
![]() |
| The launch shaft will be constructed where the 3 crawler cranes are centralised. |
![]() |
| Works outside Gleneagles Hospital. A temporary bridge will be constructed further down the road. |
![]() |
| The slurry treatment plant would likely be located where the piling rig sits. The earthworks in the foreground are likely preparations for future traffic diversions |
Wednesday, 9 April 2014
Napier - Final Preparations
We go aerial at the NPR site today. Contract T217 oversees the construction of Napier station and the adjacent tunnels to Orchard Boulevard. The site has already seen repetitive sewer diversions around the junction of Napier/Cluny Road as mentioned in the previous update. The area south of the station where the launch shaft is to be located has been cleared as well. The site office is located at the western end of the site.
Contract T217
Napier station will be stacked and designed in-house by LTA, featuring 3 levels - Subway/Concourse/Upper Platform (B1), Mezzanine (B2) and Lower Platform (B3, RL82.55). The station has been designed with knock out panels for a future underground infrastructure to cut through the mezzanine level. 2 barrier-free entrances will be built on either sides of Napier Road.
Excavation of this station will be vastly relied on dynamite blasting. Due to the sensitivity of the area, noise barriers as high as 12m will be constructed around Gleneagles and MFA around the station site. The POB at Gleneagles will be demolished.
A launch shaft will be built south of the station to facilitate 2 launches by a single TBM. The TBM will be slurry-type. The lower northbound tunnel will be bored first. Upon completion of the upper tunnel, all TBM accessories will be retrieved while the shield is abandoned in situ. The upper tunnel will then be bored with a new shield.
A cross passage will be located along Sherwood road, behind the PRC's Embassy. Due to the semi stacked configuration of the tunnels, this CP will be constructed by excavation from the surface to a depth of 42m and an audit will be mined to link both levels of tunnels. The excavation site will be eventually capped and backfilled hence does not serve as an escape shaft.
![]() |
| Site overview of the station box (Looking SE) |
![]() |
| Final power grid diversions along Holland Road (looking SW) |