The Mandai Depot is nearing completion with the final structural steel works completed. Fit-out and trackworks continue, with the commencement of landscaping, fencing and driveway works since the beginning of the year. The delivery of the first passenger train to the depot is scheduled in June.
Backfilling works for LS2 and the Sembawang Airbase C&C tunnel site, as well as casting of the escape shaft 1 structure have completed to ground level. Demobilization of the T206 sites are underway.