The station achieved the basic structure completion at the beginning of the year, with backfilling works done up. RC works for the entrance and ventilation structures are progressing at ground level.
A completed portion of the staging ground has been hoarded up in preparation for partial handover to T250. The remaining uncompleted portion around launch shaft 9 will be handed over following the complete dismantling of the TBM, backfilling and casting of the trackwork access opening.
| Backfilled compacted hardcores over the completed station structure |