Saturday, 10 March 2018

Springleaf Backfill

Filling and compaction works are taking place over the completed structure of the station. Construction of the permanent utilities and carriageway of Upper Thomson Road are concurrently taking place in preparations for the Stage 3 traffic realignment scheme. Construction of entrance B2 has started.


Springleaf Station

Wednesday, 6 December 2017

Springleaf - Basic Structure Completion

Casting of the station's roof slab has almost entirely completed and waterproofing works are in progress. RC works for the roof-ground level structure at the entrances and ventilation shafts have also taken place. The team has taken back possession of the launch shaft from T207 with structural works of the tunnel in progress. Backfilling works will commence from the next quarter onwards, and the realignment of Upper Thomson Road will take place after the hacking of the d-wall panels.


Completed roof slab at Springleaf Station

Friday, 8 September 2017

Springleaf Cast (III)

Structure of the station box is largely completed with about 2/3 of the roof slab volume cast. BSC is scheduled by the end of the year.


Springleaf Station

Tuesday, 20 June 2017

Springleaf Cast (II)

Structure of the Springleaf station is taking shape with the first section of roof slab completed.


Springleaf station

Friday, 3 March 2017

Springleaf Cast

RC works for the platform and concourse level are taking place at the station box following the completion of excavation works.


Excavation works completed at the Springleaf station

Sunday, 11 December 2016

Springleaf Excavation (IV)

Excavation works are ongoing at nearing completion at the station box.


Springleaf Station

Thursday, 8 September 2016

Monday, 6 June 2016

Springleaf Excavation (II)

Deep excavation works progresses at the Springleaf Station with the S2 strut layer installed.


Sunday, 6 March 2016

Springleaf Excavation

Installation of the first layer of strut are underway, marking the start of the excavation works at the Springleaf Station. The remaining bored pile works for the southern portion of the station continues and excavation for the entire station will be in full swing by the next quarter.



Saturday, 12 December 2015

Springleaf D-walls & Piles (III)

The final D-wall panel for the Springleaf station was completed this week. Bored pile works and the deep cement mixing ground improvement activities continue across the station footprint, and the breakthrough point of the TBM drives from Tagore. Excavation works for the station will start around February after all ground improvement works have completed.

Meanwhile, excavation works have commenced along the service corridors for the ventilation shafts beneath the road decking, as well as entrance C.


Completion of the diaphragm wall at Springleaf station (December 2015)

Tuesday, 8 September 2015

Springleaf D-walls & Piles (II)

Springleaf sees the continual trenching and construction of the diaphragm wall and bored piles forming the earth retaining system, in addition to deep soil mixing activities. Excavation works have commenced at the north launch shaft which will be handed over to the T207 project. Excavation has reached the S3 layer and the launch shaft should be handed over by year end.


Excavation of the launch shaft at Springleaf station

Wednesday, 10 June 2015

Springleaf D-walls & Piles

Clear roads ahead for the Springleaf project as the southbound carriageway was successfully diverted on March 22, shortly after our previous update, completing the major road diversion works at the site. Works on the temporary earth retaining structure for the station box are now underway.


T208 Springleaf 

Wednesday, 11 March 2015

Springleaf Diverts

The first traffic diversion for the Springleaf site was implemented at the end of January earlier this year. The Sembawang-bound carriageway of Upper Thomson Road now skirts away from the shophouses, segregating the worksite into two. As the station box sits beneath the entire span of the original road, a second phase of traffic diversion to realign the Thomson-bound carriageway has been planned and expected to be implemented in the later part of this year. 

D-walling works proceed around the station box.


Aerial view of T208, Springleaf Station
The bus stops around the site have all been included with a temporary shelter despite the permanent shelter constructed but hoarded off

Thursday, 25 December 2014

Springleaf - Preparations to Divert

At the Springleaf site, construction of the ERSS on the west end of the station has completed. The project team is now preparing to stage a traffic diversion along Upper Thomson Road to construct the remaining portion of the station's retaining wall which lies below the existing road. This impending diversion is expected to be a permanent-temporary one, whereby it will last through most of the duration of the project. The diversion should take place within the next 2 months.

Due to the presence of a launch shaft at the north end that needs to be constructed and handed over to Shimizu of the neighboring contract T207, there is an urgency for the shaft to be done up swiftly. The handover is anticipated to take place around the middle of next year.


D-walling & Piling activities back in October
Preparations to divert Upper Thomson Road (Dec 22)

Tuesday, 9 September 2014

Springleaf & Tagore

As of today, 6 crawler cranes and 1 piling rig lies at the Springleaf site. A hydromill trench cutter has been attached to one of the cranes, marking the start of excavation for the diaphragm walls.

Trench excavation process
2 cutting drums are attached to the base of the trench cutter, operating in reverse circulation as it excavates the earth. As it excavates, soil is loosened, broken down and mixed with a support fluid which is then pumped to the desanding plant at the surface via mud pumps. The slurry is then cleaned and subsequently recirculated into the trench.


Springleaf Station
Tagore station

Wednesday, 18 June 2014

Springleaf & Tagore

Contract T208 is the only TSL contract to have 2 stations under its scope of works. Springleaf station will be operational when the line is completed. The second station of Tagore will only have its basic structure ready and remain closed. Plans to rejuvenate the existing Ang Mo Kio town will see a phased expansion into the existing forest beyond Lentor. Its aesthetics and fittings will only be done up when there is sufficient demand from the new private residential estate.

In the meantime, the Tagore box will function very similar to the current Hume station along the Downtown Line. 4 TBMs will launch out of Tagore towards Springleaf and Lentor. Upon completion of tunnelling works, the Tagore site will be prepared as a temporary staging area for trackworks. There will be 3 cross passages between Springleaf and Tagore, and another 3 between Tagore and Lentor. 2 CPs will be integrated into the Tagore station.

Numerous crawler cranes have been delivered to the site at Springleaf. As of now, the trees along Upper Thomson have not been felled as earthworks are concentrated on the west side where the site office sits. Site clearing can be distinctively seen at Tagore as well.


Update preview - Springleaf station
Update preview - Tagore station

Thursday, 3 April 2014

Springleaf - Start is here

Contract T208 is for the construction of Springleaf station and tunnels to Lentor station. Site clearing has commenced at the station location and the site office is mostly completed.



Friday, 15 November 2013

Contract Awards - T208 & T212

The LTA has awarded two contracts for the Thomson Line (TSL) today - T208 for construction of Springleaf station and T212 for construction of Upper Thomson station. T208 is awarded to the Leighton-John Holland Joint Venture (currently doing C935 Jalan Besar station on DTL3). T212 is awarded to Sato Kogyo (currently doing C928 Bedok North, C932 Mattar and C936 Bencoolen stations on DTL3). Also issued were some renders of the stations.

Springleaf

View of the entrance at Springleaf station
Platform view at Springleaf station

Upper Thomson

View of the entrance of Upper Thomson station
Platform view at Upper Thomson





Construction begins in the first quarter of 2014 for completion in mid-2020.