Saturday, 3 March 2018

Woodlands North Fit-Out

Structure of the north crossover tunnel has been completed. Preparations for the realignment of Admiralty Road West is in progress over the completed structure with implementation due by June. The remaining RC structure for the overrun tunnel will proceed following the road reinstatement. 

RC superstructure works are in progress at the 2 ventilation structures. Structure of entrance D is mostly completed, and fit out works within the station are being carried out.


Woodlands North

Friday, 1 December 2017

Woodlands North - Basic Structure Completion

The Woodlands North station is on track to achieve the Basic Structure Completion (BSC) by year end as scheduled, a milestone concluding the main civil & structural reinforced concrete works. The BSC also governs the necessary waterproofing, temporary lighting, drainage and general housekeeping to be in place for the safety of the system wide contractors (SWCs) to commence the architectural and M&E works.

Structural works are in progress for the 2 entrances as well as the north crossover tunnel. Backfilling works progress across the south crossover tunnel and launch shaft area. A second stage of earthworks have commenced by the authorities east to the T202 site in preparation of business, industrial and commercial developments around the station, including the upcoming JBRTS complex.


Completed structure of the Woodlands North station

Friday, 1 September 2017

Woodlands North Cast (V)

Structural works for the station box are largely completed at the roof level and BSC is targeted by the end of the year. Casting of the north crossover tunnel is ongoing.


T202 Site overview

Tuesday, 13 June 2017

Woodlands North Cast (IV)

Casting of the concourse slab at the station is largely completed and structural works are progressing up to the roof level of the station. The south crossover tunnel is completed and filling works are taking place to the roof level. Structural works on the overrun tunnel are underway.


Filling works at the completed south crossover tunnel

Monday, 27 February 2017

Woodlands North Cast (III)

Casting work continues at the Woodlands North site. The platform level of the station is completed and formwork is being propped for the casting of the concourse level. Structure of the north crossover tunnel is forming up.


South crossover tunnel structure nearing completion

Wednesday, 7 December 2016

Woodlands North Cast (II)

Casting work continues at the Woodlands North site. All ground improvement works have been cleared at the north crossover tunnel site and casting works are commencing there. To the south, casting works for the south crossover tunnel roof and walls are nearly completed. The underplatform level of the station box has been completed.



Casting ongoing at the south crossover tunnel

Thursday, 1 September 2016

Woodlands North Cast

Casting of the station's underplatform level is in progress. The tunnel walls for the south crossover tunnel have been concreted, and casting of the roof and subsequent waterproofing works are taking place as the concreting works progresses southwards. Both TBMs are nearing the completion of their tunnel drives to Woodlands station.


T202 Woodlands North Station

Thursday, 2 June 2016

Piling at Woodlands North (IV)

Bored piling for the station's foundation has completed, while the bored pile works continue northwards at the overrun tunnel and casting of the south crossover tunnel are progressing.

Casting of the base slab and tunnel walls for the diamond crossover south of the station

Tuesday, 1 March 2016

Piling at Woodlands North (III)

Piling works, together with minor excavation and casting works progress at the Woodlands North site.



Saturday, 28 November 2015

Woodlands North - TBM Launch

The TBM launching ceremony at the Woodlands North site was held today. The ceremony was celebrated on Saturday by Penta Ocean and the LTA ahead of the commencement of excavation works by the Changi Bound TBM on Monday. The TBMs here will launch with the full ancillary equipment pre-installed, most notably including the backup gantries. 

Extremely seldom do the space and site conditions permits for such convenience, and would usually require the adjacent cut-and-cover structure to be excavated to the equivalent formation level. However the uniqueness of the terrain at the Woodlands North site grants the complete assembly of the machine prior to launching.

Piling works continue at the station. Construction of a new sewer mains is also taking place at the north end of the site along Admiralty Road West, and will run alongside the length of the station box. Ground improvement works continue along the tunnel route at the diverted Woodlands Dr 91, outside Republic Polytechnic.


Launch of the first 2 Kawasaki Slurry TBMs
T202 TBM launching ceremony (Nov 28) 

Monday, 31 August 2015

Woodlands North - TBM Assembly

The first Kawasaki slurry TBM has been assembled at Woodlands North for the T202 project. Supporting the impending tunnelling works are the installation of the backup gantries and gantry cranes at the launch shaft. The 2nd TBM has also been delivered to the site. Tunnelling should commence by the end of the year.

Excavation of the crossover tunnel adjacent to the launch shaft is about complete, and its site is temporarily housing the backup gantries for both TBMs. The formation level of the tunnel here matches the existing ground level of the site due to the earthworks slope treatment and the natural shallow design of this project. Rockheads are visible on either sides of the structure.

Piling works are ongoing at the station box and north crossover tunnel.


T202 Woodlands North, August 31
Assembly of TBM1

Monday, 1 June 2015

Piling at Woodlands North (II)

Commencing the Q2 updates at the Woodlands North site, numerous piling rigs are executing the bored pile works for the station's earth retaining stabilizing structure. Towards the south, excavation of the launch shaft has reached down to the S3 layer.

The first Kawasaki TBM for the T202 project has been delivered to the site. Supporting the slurry TBM for the upcoming tunnelling work is the assembled slurry treatment plant provided by Pigott Shaft Drilling. Deep Cement Mixing and grouting is being carried out along the proposed tunnel alignment at Woodlands St 91.


TBM 1 and Slurry Treatment Plant delivered next to the launch shaft

Sunday, 1 March 2015

Piling at Woodlands North

We begin another quarter's update on the progress of the Thomson Line construction at Woodlands North. A long auger drilling machine has arrived onto the site and positioned near the launch shaft. Beside it, several pile casings and rebar for the bored pile lay on the site floor. A desander plant seems to be in the process of being set up as well. At the launch shaft itself, piling has commenced with a concrete bored pile guide constructed to aid the drilling process. Earthworks are still being carried out at the crossover tunnel and station box.


Aerial view of Republic Polytechnic and the Straits of Johor bounding the Woodlands North site 
Drilling machine, pile casings and rebar beside the U/C desander plant next to the launch shaft

Monday, 15 December 2014

Woodlands North Terraced

Penta Ocean has almost completed flattening the hill and a little valley has been paved where the rail structure is to be built beneath. The slope along the hills have been terraced into sections with much resemblance to the Caldecott site which shares a similar terrain. Piling works have commenced at the launch shaft by the contractor, while preliminary soil investigation works have begun along the tunnel route from WDN to WDL station.

Kawasaki will be supplying Penta Ocean's Contract T202 with 2 slurry TBMs for the drives from Woodlands North to Woodlands Station, while Pigott Shaft Drilling will supply the slurry treatment plants for the 2 machines.

Woodlands North Site

SI works along the southbound tunnel route, opposite Republic Poly near the launch shaft

Monday, 1 September 2014

Woodlands North Earthworks

Woodlands North station sits on one of the most hilly terrains across the island. As such, terracing works are needed to flatten the existing land before structural works can begin. The granite obtained from the blasting works during the earthworks and excavation process will be recycled into composites for concrete to be used back when constructing the station, in the effort to minimize project cost. 

The cut and cover portion for the contract is extremely long (750m) due to the presence of a north and south crossover, as well as an abutting overrun tunnel for the Changi Bound track which will be constructed beyond Admiralty Road West. A road diversion will be needed.


Aerial view of Woodlands North 

Bored tunnels will follow St 81 before docking at Woodlands

Tuesday, 20 May 2014

Slowly starting in Woodlands North

The first station site on the line, located next to the Republic Polytechnic, is seeing a dramatic change as the greenery gives way to the earthy brown tones. Trees are being cleared to make way for the station site along with a new road system in the area. Once a forested area with a tree-covered hillside, the area is now being leveled after the trees have been felled.


A once forested hillside


An overview of the station area, looking northwards from the HDB blocks at Woodlands St 81.

Looking eastwards from the RP multi-storey carpark at the site office

Saturday, 1 February 2014

Woodlands North pre-construction

Several photos of the future site of Woodlands North station before construction commences.

This area will be cleared and developed in several years to come.

Saturday, 30 November 2013

Contract Awards - T202 & T217

Yesterday the Land Transport Authority announced the final civil contract awards for the Thomson Line (TSL) due this year - contracts T202 and T217. Contract T202 is for the construction of Woodlands North station with over-run tracks and bored tunnels to Woodlands interchange. There will be a scissors crossover before the station as well. This contract was awarded to Penta-Ocean Construction Ltd who is currently building Bendemeer station on Downtown Line 3 (DTL3).


Artist's impression of the entrance at Woodlands North station. There will be two exits and multiple knock out panels here.
The interior of Woodlands North is spacious, with lots of escalators to cater for crowds accessing the JB RTS system.

Contract T217 is for the in-house designed Napier station at the junction of Napier and Cluny Roads. This contract involves construction of the stacked side station with two entrances and stacked bored tunnels to Orchard Boulevard station. Sinohydro Co has received the award and this will be the first time they are involved in an MRT project here in Singapore. Their previous track record lies in Guangzhou and Tianjin in China.

A view of the entrance outside Gleneagles Hospital.
Napier station will see the concourse and upper platform (South-bound) sharing the same level. The lower platform is 2 levels down.
That concludes the expected awards for this year, though LTA may continue to award other contracts next month. For now, here is a recap of the contracts and the companies awarded for the civil construction thus far:

T201 - Jurong Primewide
T202 - Penta-Ocean
T203 - GS E&C
T205 - Woh Hup Pte Ltd
T206 - Shanghai Tunneling Engineering Company
T208 - Leighton - John Holland JV
T209 - China Railway No 5 Engineering
T210 - Gammon Construction
T212 - Sato Kogyo
T213 - Samsung C&T
T217 - Sinohydro