Bulk excavation works in full swing at the cut and cover tunnel |
D-wall works |
Bottom up excavation works across the CCT |
Progress is skewed with excavation at the S4 layer towards the station interface |
Excavation works at the station |
RC works at the concourse (Photo: Bachy Soletanche) |
Replacement TBM shields and cutter stored at the shaft surface |
Mining works beneath Orchard Boulevard road |
Bored pile works along ION |
Stage 5 traffic diversion (3-phase diversion for the SBP construction of the unpaid linkway to Wheelock) implemented |
TBM S-963 main drive now past 200 rings (Changi bound ~50% completed) (Photo: Bachy Soletanche) |