Showing posts with label TE17 - Outram Park. Show all posts
Showing posts with label TE17 - Outram Park. Show all posts

Friday, 22 December 2017

Outram Park Cast (V)

Excavation works progresses along the linkways & casting works at the station.


Outram Park Station

Thursday, 5 October 2017

Outram Park Excavation (III)

Excavation works across the network of new unpaid and paid linkway are progressing across the site. The project's second and final TBM relaunch took place at the end of Q3 for the Changi bound tunnel drive towards Havelock.


T222 Outram Park

Wednesday, 12 July 2017

Outram Park Cast (IV)

Structure of the station has reached the underplatform level. Excavation of the linkways and initial drive of the Woodlands bound TBM towards Havelock are in progress.


T222 Outram Park site

Sunday, 16 April 2017

Outram Park Excavation (II)

The concourse slab has been cast and excavation works for the station are now at the platform level of the station. The final realignment of Outram Road was carried out last month for the excavation of the new interchange linkways, and would remain in position till the end of the project. TBM2 has almost completed the Changi bound tunnel towards Maxwell.


TBM 1 re-assembly works at launch shaft towards Havelock

Monday, 26 December 2016

Outram Park Excavation

Excavation and casting works are progressing at the station box.


T222 Outram Park

Tuesday, 4 October 2016

Outram Park Cast (III)

Completion of the last zone of roof slab took place concurrent with the demobilization of the D-wall grabs and ancillary silo & slurry equipment in August. Bulk excavation works are now underway at the Outram Park station.


Bulk excavation works across the Outram Park station

Tuesday, 21 June 2016

Outram Park Cast (II)

Casting of the roof slab continues to take place in phases northwards, while works on the diaphragm wall are still being carried out. A minor realignment of Cantonment Road took place end April for the piling works along the interchange linkway.



Monday, 11 April 2016

Outram Park Cast

The roof slab of the station is progressively being constructed from the south while the d-walling works continues along the new linkway. Both NFM EPBMs arrived on the site at the beginning of March, and the first TBM was lowered down the south shaft 2 days later. The machine is currently being assembled up.


Overview of the T222 site with the d-wall of the Outram Park station mostly completed

Tuesday, 29 December 2015

Outram Park D-walls (II)

Works on the diaphragm wall and bored pile continues at the Outram Park station and linkway. Excavation and shoring works have also commenced at both launch shafts. The 3rd project information center for the Thomson-East Coast Line's civil team 4 has opened to public at the project office here.



Saturday, 10 October 2015

Outram Park Diverts

Several realignments along Eu Tong Sen St and New Bridge Road have been implemented at the Outram Park station site following the relocation of the ERP gantry. The slip road from Outram Road has been diverted beneath the roof of the NEL entrance to allow piling works to take place for the new interchange paid linkways. A realignment along the CTE bound Outram Road is currently being prepared as well.

Pearls Centre have been vacated by the last quarter, and removal of the exterior cladding have commenced under the first phase of the demolishment works. Works on the diaphragm wall continues for the Outram Park station.


Diversion of Eu Tong Sen St & New Bridge Road and upcoming diversion being prepared along Outram Road

Tuesday, 21 July 2015

Outram Park D-walls (II)

The Pedestrian Overhead Bridge along Outram Road was successfully demolished on May 24 and most recently July 12 along the CTE bound and Cantonment bound carriageway respectively. This is the 4th POB to be demolished along Thomson Line project. In addition to preparations works for the upcoming numerous road diversions for the construction of the interchange linkway is the relocation of the ERP gantry along Eu Tong Sen Street.

Majority of the shops within Pearls Centre have started to vacate following the management's decision to cease all tenure lease by the end of this quarter. Demolishment of the complex can be expected by the first half of next year. D-walling and piling works continue around the site area.


Column remain of the demolished POB linking HSA to the existing station

Friday, 17 April 2015

Outram Park Hoards Up

Hoardings have started to come up around the surface of the existing Outram Park EWL station and Outram Road. A section of the iconic red covered walkway linking Pearls Centre to the EWL station has also been closed and demolished. D-walling works continue at the station.

The temporary POB across Outram Road is structurally completed and is slated to be operational by the end of the month. The temporary bridge will be accompanied by an elevator on both ends to provide barrier free access from the existing MRT station to the HSA and SGH. The existing bridge will then be demolished.

Across the road, several silos and a piling rig have been positioned at the HSA where 6m high hoardings have been installed.


Hoardings around Outram Road as well as the HSA
Temporary POB awaiting to be commissioned

Thursday, 22 January 2015

Outram Park D-walls

Activities at the T222 Outram Park site has hyped up with the commencement of the D-walling works for the station. A hydrofraise, along with several crawler cranes and rebar cages scatters the site floor. The silt treatment plant is built next to Pearl's Centre.

Along Outram Road, 2 nights of beam launching works were facilitated over the past 2 weekends for the temporary POB that will replace the existing bridge that is to be demolished. The beam segment across the CTE and Cantonment bound carriageway were launched up on January 11 & 18 respectively. This is the third temporary POB to be built for the Thomson Line.

Construction signage, along with interlocking road barriers have been prominently placed around Eu Tong Sen Street and Outram Road, where utility diversions and the felling of small trees are currently taking place. The mentioned works seen around the corner of the two road's intersection are preparatory to facilitating future traffic diversions - for the construction of the new interchange linkages.


T222 Outram Park
Hydrofraise for the D-walling works
Temporary POB across Outram Road

Sunday, 5 October 2014

Outram Park Assembles

Contract T222 is for the construction of Outram Park station and 2 twin bored tunnels to Havelock and Maxwell. The station is situated on an empty plot of state land north of the existing East West Line. The contract was awarded to Daelim Industrial. They have previously worked under Contract 487 of the Marina Coastal Expressway and this is their second project for the Client.


Site overview
Proposed TSL box parallel to the existing East West line (left)
Outram Park Station
The new station will have a very similar layout to its EWL counterpart. There will be 3 levels - a Concourse, Platform and Transfer level. An additional 2 entrances will be built along Outram Road to complement the existing interchange. Entrance A will be located near Pearl Bank, while Entrance B provide doorstep connectivity to the Health Sciences Authority. The station will be constructed top-down.

A&A to existing RTS
There will be an overhaul in the linkage design within the existing interchange. The new changes include:
- 1 new dedicated NEL-EWL paid link with 4 travellators
- 1 new dedicated NEL-TSL paid link to be extended from the existing NEL-EWL linkage
- 1 new EWL-TSL paid link to be constructed beneath both platforms on the transfer level. 2 new escalators will be installed down from the west end of the existing EWL platform for this linkage.
- 1 new unpaid link between all 3 lines to be constructed on the concourse level with 4 travellators

Outram Road which would see intensive phased traffic diversions to build the new linkages
New Entrance B to be built infront of HSA and enhance connectivity to the interchange station
Tunnelling
2 launch shafts will be constructed on either ends of the station box. 2 EPB TBMs will be procured under this contract. The TBMs will do an initial north drive to Havelock station before docking, dismantling and reassembling for the second drives to Maxwell at the south. The alignment of the TSL tunnels to Havelock run directly beneath the existing EWL tunnels for a good 500 meters. A cross passage will be located here. Similar to contract T212 at Upper Thomson, this will be the first time excavation of a tunnel parallel and beneath and existing operational MRT tunnel is being executed here.

Tunnels to Maxwell will go beneath the existing footings of shophouses near Kreta Ayer

Update Progress
The site office has just been completed and is located behind the soon to be demolished Pearls Centre. Works are midway to surface the slab on the site ground. On areas with the completed slab, the bentonite plant and silos have been erected. Trench Cutters are also being assembled on the site.

T222 Site office at 102A Eu Tong Sen St
Pre-assembled trench cutters and erected bentonite silos

Tuesday, 27 May 2014

Contract Awards - T218, T220, T222 & T225

Today the Land Transport Authority announced the award of 4 contracts to build stations and associated tunnels. With the award of these 4 contracts, there only remain 3 such contracts for all stations to be awarded to contractors.

The first award is for contract T218, involving the construction of Orchard Boulevard station only. This contract has gone to local company KTC that is currently working on the Tampines Central station on the Downtown Line.

The first render issued of Orchard Boulevard station. It lacks certain details made more prominent in subsequent renders.

Wednesday, 20 November 2013

Outram Park Pre-Construction

Outram Park has changed over the last 20-odd years since the first works for the MRT in Singapore began. In the 80's, work began on construction for the original network with the East-West Line (EWL) being built. In the 90's, work on the North-East Line (NEL) commenced. The decade of the 2000s saw the area being given a break from all rail construction work. 

Now in the 2010's, the Thomson Line (TSL) is set to open up the area once again as the Outram Park interchange is built. Along with the TSL station, major modification works to the existing EWL and NEL stations will be done, including extensive re-configuration of the transfer linkways. Here are some photos before any works commence on the site.


24 March 2013