Casting works for the station have reached the platform level where all excavation works have completed. The project is currently one of the quickest along the line, with the station and entrances seemingly on track to achieve basic structural completion next year - ahead of the indicative 2018 target.
Basement roof slab completed at Entrance D |
Entrance C |
Strut removal at Entrance G |
Entrance E RC works |
Subway to Entrance A & F roof slab |
Entrance F casting works |
Entrance A |