Bulk excavation works for the Havelock station have finally started and should continue till the second half of 2017 for the bottom up construction of the station. Tunnelling works for the rectangular box jacking machine completed in mid November, and dismantling of the machine is in progress.
|
Commencement of excavation works for the station box |
|
150m Box-jacked subway tunnel completed between the station box and Havelock Road |
|
DCM |
|
Final ring segments jacked into position |
|
RC works at the entrance (left) |
|
Segment cast in-situ yard demobilized |