Piling works have intensified across the Mount Pleasant station site, with additional piling rigs brought to the site increasing the total count of 9. 5 mobile cranes are supporting the bored pile process in addition to the 2 crawler cranes.
Over the past quarter, the south launch shaft had successfully been excavated down 5 levels and had just been completed by the T215 team. The launch shaft is now anticipating a handover process to the T216 project which will facilitate the tunnel works to Stevens.
The north launch shaft had just commenced excavation and should be ready by year end.