Sunday, 11 March 2018

Tagore Trackworks

CTCI has taken full possession of the staging ground from T208 since the beginning of the year. 2 gantry cranes have been assembled at the site, with track-laying equipment being brought in ahead of the commencement of trackworks towards Lentor Station.


T250 site mobilization activity at Tagore

Saturday, 9 September 2017

Tagore Backfill (II)

The Tagore site has begun demobilization works by the T208 team as it prepares to handover the site to CTCI and other SWCs for the temporary staging area works between Tagore and Mount Pleasant. The STP and gantry cranes have been demobilized, with hardcore compacted above the station box. The FSC, cross passage and bracket installation works are ongoing for the twin tunnels towards Springleaf.


Tagore C&C site

Tuesday, 20 June 2017

Tagore Backfill

Filling works are in progress over the completed structure at Tagore which would site the 1 hectare trackworks staging ground to come. The final TBM C2 is about 75% completed and will complete by the next quarter.


Backfilling works and de-strutting over the concourse slab 

Sunday, 5 March 2017

Tagore Cast (IV)

Structure of the concourse slab is mostly completed for the station box. TBM B drive is over 85% completed now and breakthrough at Springleaf is expected in early Q2. TBM C2 will follow suit a quarter later. Staging works for trackwork will commence at Tagore by year end with handover of site possession to CTCI at the later part of the year.


Concourse slab cast at Tagore

Monday, 12 December 2016

Tagore Cast (IV)

Casting of the concourse and platform structures are ongoing at Tagore.

TBM B Progress - R504 (706m, 64% completed)
TBM C2 Progress - R367 (514m, 47% completed)


Tagore C&C tunnel

Saturday, 10 September 2016

Tagore Cast (III)

TBM C was relaunched in July. The removal of the temporary rings and reaction frame at the lauch shaft last month completes the TBM's conversion to its main drive. TBM B is now halfway through its tunnel drive to Springleaf and under the Seletar Expressway. The concourse slab at Tagore has been cast.


TBM B and TBM C2 progress as of September 8

Tuesday, 7 June 2016

Tagore

Twin bored tunnels to Lentor station have been completed by TBM A and TBM C1. TBM B is now 230 rings into the Woodlands Bound excavation to Springleaf, a third of the tunnel lined. TBM C2 is in the midst of assembly and refitting works for the Changi bound drive.



Sunday, 13 March 2016

First Tunnel Completes

The first TBM that was launched from Tagore in August last year has completed excavation works at the Lentor station. The NFM-made slurry machine has performed a remarkably fast drive for the 1.1km northbound tunnel, with the final 85% (~1km) stretch of the tunnel completed within just 3 months. The TBM's backup gantries will begin to be dismantled and brought back to the Tagore site through the completed tunnel, before being refitted into the new TBM shield for the second drive.

The body of the existing TBM will be left underground and be integral to part of the permanent lining of the tunnel structure after it is lapped over with reinforced concrete segments, while dismantling of the cutterhead will be done once excavation on the Lentor side has reached the formation level.


TEL1/2 Tunnel Chart, March 2016

Monday, 7 March 2016

Tagore Cast (II)

The completion of the first bored tunnel for the Thomson Line is coming up within the T208 project. The drive executed by TBM C for the northbound tunnel between the Tagore C&C and Lentor Station is over 90% completed. Maintaining an advance of an average of close to 8 rings per day since the start of the year, excavation of the tunnel is envisaged to complete by the middle of March.

The replacement cutterhead and TBM shield for TBM C has already been positioned at the surface of the north launch shaft in preparations for the second drive towards Springleaf.


French secretary of state for transport Alain Vidalies visiting the NFM TBMs at the Tagore C&C tunnel site in February (photo: NFM)

Monday, 14 December 2015

Tagore Cast

Excavation at the Tagore cut and cover tunnel has completed and the base slab has been concreted between GL5-7. Excavation of the tunnels between TGR and LTR are progressing. The Woodlands bound tunnel is now at ring 99 (12% completed). The TBM boring the Changi bound tunnel is experiencing problematic ground conditions over the past month, and regular interventions are being carried out to unclog the cutters (ring 60, 7% completed)

TBM B is in the process of assembly works at the second launch shaft and tunnelling works to Springleaf for the Woodlands Bound tunnel should start by January.


Assembly works for TBM B

Thursday, 10 September 2015

Tagore Excavation

Excavation works at the Tagore C&C tunnel site is nearing completion. The north launch shaft is completed as well and sees the recent installation of the second gantry crane at the site. The third and final TBM should arrive by this month and tunnelling works towards Springleaf could commence by year end.

Precast lining segments are visible at the south launch shaft facilitating the recent commencement of tunnelling works towards Lentor. The second TBM is believed to still be undergoing alterations to the internal electrical components and should commence mining within the next few days.



Thursday, 11 June 2015

Tagore - TBM Assembles

The first NFM TBM for the T208 project has begun assembly works within the launch shaft. The TBM will be executing an initial drive on the Woodlands bound tunnel towards the retrieval shaft at Lentor. As of Monday, the main shields and backup gantries have been lowered while the cutterhead remains on the surface of the shaft. The gantry crane has been assembled as well. Tunnelling works should commence in a month's time.

Piling across the Tagore C&C have completed and the first layer of strut have been installed across the entire span of the structure.


TSL1/2 Tunnel Chart, June 2015
Tagore C&C

Friday, 13 March 2015

Tagore Piles & Excavates (II)

The south launch shaft, together with a short portion of the adjacent cut and cover tunnel has been successfully excavated to the formation level (approx RL 99.000m). 4 layers of struttings have been constructed to support the 20m deep earth retaining structure. In addition, a pre-assembled gantry crane has been delivered and presently lies next to the shaft. The Slurry Treatment Plant (STP) has been assembled on site.

Inaugural bored tunnelling works for the Thomson Line look set to commence at the Tagore site around the middle of this year. 2 NFM Technologies TBMs will be launched from this shaft and driven 1.1km southwards to a retrieval shaft at the Lentor station. Upon breakthrough of the first tunnel, the first machine will be retrieved and re-assembled back at Tagore for a second drive towards Springleaf. 

Sites for the ground improvement works above the 3 cross passages (CP8D, CP9 & CP10) between Tagore and Lentor is evident from the aerial shots. Secant bored pile works continue around the north launch shaft and C&C tunnel.


Tagore Cut and Cover, T208

T208, Mix ground conditions along the tunnel route that the TBMs will interface (Cr: Noma)

Saturday, 27 December 2014

Tagore Piles & Excavates

Tagore is currently leading in progress due to the large number of equipment brought in by Leighton-John Holland. The ERSS along the south side of the station and launch shaft has completed and excavation works have begun, with the first layer of struts have been installed. Ground treatment works are being done beside the launch shaft as well. Piling works continue at the north side and a desander plant is being constructed next to the Tagore site office.

NFM Technologies has been chosen as the manufacturer to supply 3 Slurry TBMs for T208. Upon completion of the first tunnel towards Lentor, 1 machine will be redriven in the direction of Springleaf. Pigott Shaft Drilling shall supply the slurry treatment plants for the 3 slurry shield machines.


9 piling rigs, 3 crawler cranes and a mobile crane mobilized at the Tagore site
Mock up of 1 one of the 3 NFM Slurry TBMs to be used for T208

Tuesday, 9 September 2014

Springleaf & Tagore

As of today, 6 crawler cranes and 1 piling rig lies at the Springleaf site. A hydromill trench cutter has been attached to one of the cranes, marking the start of excavation for the diaphragm walls.

Trench excavation process
2 cutting drums are attached to the base of the trench cutter, operating in reverse circulation as it excavates the earth. As it excavates, soil is loosened, broken down and mixed with a support fluid which is then pumped to the desanding plant at the surface via mud pumps. The slurry is then cleaned and subsequently recirculated into the trench.


Springleaf Station
Tagore station

Wednesday, 18 June 2014

Springleaf & Tagore

Contract T208 is the only TSL contract to have 2 stations under its scope of works. Springleaf station will be operational when the line is completed. The second station of Tagore will only have its basic structure ready and remain closed. Plans to rejuvenate the existing Ang Mo Kio town will see a phased expansion into the existing forest beyond Lentor. Its aesthetics and fittings will only be done up when there is sufficient demand from the new private residential estate.

In the meantime, the Tagore box will function very similar to the current Hume station along the Downtown Line. 4 TBMs will launch out of Tagore towards Springleaf and Lentor. Upon completion of tunnelling works, the Tagore site will be prepared as a temporary staging area for trackworks. There will be 3 cross passages between Springleaf and Tagore, and another 3 between Tagore and Lentor. 2 CPs will be integrated into the Tagore station.

Numerous crawler cranes have been delivered to the site at Springleaf. As of now, the trees along Upper Thomson have not been felled as earthworks are concentrated on the west side where the site office sits. Site clearing can be distinctively seen at Tagore as well.


Update preview - Springleaf station
Update preview - Tagore station