Friday, 17 August 2018

LTA Update (Q2 2018)

T205 Woodlands South Station. Escalators installed between the paid concourse down to the platform level.

Monday, 7 May 2018

Tuesday, 6 March 2018

Launch Shafts Backfill

The Mandai Depot is nearing completion with the final structural steel works completed. Fit-out and trackworks continue, with the commencement of landscaping, fencing and driveway works since the beginning of the year. The delivery of the first passenger train to the depot is scheduled in June.

Backfilling works for LS2 and the Sembawang Airbase C&C tunnel site, as well as casting of the escape shaft 1 structure have completed to ground level. Demobilization of the T206 sites are underway.


Mandai Depot

Monday, 5 March 2018

Woodlands South - Basic Structure Completion

The station achieved full basic structural completion with final portion of roof slab cast at the beginning of the year. The remaining concourse and roof slabs have also been constructed at the temporary access pits. RC structural works for entrance B & D have completed, and trackworks have also progressed through the station from SBAB.


Installation of steel lift frame and backfilling of earth around entrance A

Sunday, 4 March 2018

Woodlands - Basic Structure Completion

The final zone of roof slab has been constructed, completing the main structural works at the station. Dismantling of the temporary struts, kingposts, waler beams as well as the striking of falsework are in progress following which the station would achieve the BSC. Structural works for entrance F have also completed to the threshold level - the first among all 5 entrances.


Woodlands Station

Saturday, 3 March 2018

Woodlands North Fit-Out

Structure of the north crossover tunnel has been completed. Preparations for the realignment of Admiralty Road West is in progress over the completed structure with implementation due by June. The remaining RC structure for the overrun tunnel will proceed following the road reinstatement. 

RC superstructure works are in progress at the 2 ventilation structures. Structure of entrance D is mostly completed, and fit out works within the station are being carried out.


Woodlands North

Monday, 4 December 2017

Mainline Trackworks

Trackworks at the depot have been ongoing for over a year now, with majority of the works mostly completed across the depot. CTCI has begun taking over access along the completed portions of tunnel between T206-T208, with trackworks commencing along the reception tunnels 1&2 towards Sembawang Airbase. The permanent tunnel structure within the launch shafts are being constructed over as a conclusion to the civil works.


Mandai Depot

Sunday, 3 December 2017

Woodlands South Cast (III)

Casting works for the station are now progressing along the internal RC partition and skinwall at the platform and concourse levels up to the roof structure.


Removal of S1 strut & basement roof - ground structure emerging at entrance A

Saturday, 2 December 2017

Woodlands Cast (V)

The first section of the roof slab has been cast and reinforcement works for the second zone has almost been completed in preparations of the second pour. Casting works are ongoing at the entrances and crossover tunnel. 2 steel beam launching works for the NSL paid linkway was carried out over the last 2 months.


T203 Woodlands Station with roof slab completed around GL14-18

Friday, 1 December 2017

Woodlands North - Basic Structure Completion

The Woodlands North station is on track to achieve the Basic Structure Completion (BSC) by year end as scheduled, a milestone concluding the main civil & structural reinforced concrete works. The BSC also governs the necessary waterproofing, temporary lighting, drainage and general housekeeping to be in place for the safety of the system wide contractors (SWCs) to commence the architectural and M&E works.

Structural works are in progress for the 2 entrances as well as the north crossover tunnel. Backfilling works progress across the south crossover tunnel and launch shaft area. A second stage of earthworks have commenced by the authorities east to the T202 site in preparation of business, industrial and commercial developments around the station, including the upcoming JBRTS complex.


Completed structure of the Woodlands North station

Friday, 10 November 2017

November Tunnel Progress

Bored tunnelling works progresses across the line, with multiple TBM breakthroughs due around the new year of 2018. The Changi bound tunnel was completed at Orchard last month, completing all bored tunnel works under the T219 project - the first project to do so along TEL3.

TBMs with envisaged completion between Dec 2017 and Jan 2018:
T209 TBM 1&2
T212 TBM 1
T215 TBM S-936
T227 TBM 1
T228 TBM 1

TEL1/2 November Tunnel Progress (No change since Sep)

Tuesday, 5 September 2017

Sembawang Airbase Backfill

Backfilling works are underway at SBAB upon completion of the tunnel roof structure. As the installation of the SWC brackets in the tunnels complete by the next quarter, the interlinking tunnel structure within each launch shaft will be cast to provide a complete substructure tunnel linkage across TEL1 for trackworks to proceed on to the reception tracks and mainline from Mandai Depot.


S1-S2 removal with concurrent backfilling works at Sembawang Airbase C&C

Monday, 4 September 2017

Woodlands South Cast (II)

A final realignment of Woodlands Avenue 1 has been implemented for the excavation and construction of Entrance D, the last of the 4 entrances to be built. Structure of the station has reached the platform level, and the superstructure of Entrance A is emerging from ground level.


Woodlands South Station

Sunday, 3 September 2017

Woodlands Cast (IV)

Casting of the station's concourse slab is largely completed and works are proceeding up to the roof level. Excavation works at the crossover tunnel site have completed facilitating the breakthrough of the T206 tunnels.


T203 Woodlands 

Friday, 1 September 2017

Woodlands North Cast (V)

Structural works for the station box are largely completed at the roof level and BSC is targeted by the end of the year. Casting of the north crossover tunnel is ongoing.


T202 Site overview