Tuesday, 6 March 2018

Launch Shafts Backfill

The Mandai Depot is nearing completion with the final structural steel works completed. Fit-out and trackworks continue, with the commencement of landscaping, fencing and driveway works since the beginning of the year. The delivery of the first passenger train to the depot is scheduled in June.

Backfilling works for LS2 and the Sembawang Airbase C&C tunnel site, as well as casting of the escape shaft 1 structure have completed to ground level. Demobilization of the T206 sites are underway.


Mandai Depot

Monday, 4 December 2017

Mainline Trackworks

Trackworks at the depot have been ongoing for over a year now, with majority of the works mostly completed across the depot. CTCI has begun taking over access along the completed portions of tunnel between T206-T208, with trackworks commencing along the reception tunnels 1&2 towards Sembawang Airbase. The permanent tunnel structure within the launch shafts are being constructed over as a conclusion to the civil works.


Mandai Depot

Friday, 10 November 2017

November Tunnel Progress

Bored tunnelling works progresses across the line, with multiple TBM breakthroughs due around the new year of 2018. The Changi bound tunnel was completed at Orchard last month, completing all bored tunnel works under the T219 project - the first project to do so along TEL3.

TBMs with envisaged completion between Dec 2017 and Jan 2018:
T209 TBM 1&2
T212 TBM 1
T215 TBM S-936
T227 TBM 1
T228 TBM 1

TEL1/2 November Tunnel Progress (No change since Sep)

Tuesday, 5 September 2017

Sembawang Airbase Backfill

Backfilling works are underway at SBAB upon completion of the tunnel roof structure. As the installation of the SWC brackets in the tunnels complete by the next quarter, the interlinking tunnel structure within each launch shaft will be cast to provide a complete substructure tunnel linkage across TEL1 for trackworks to proceed on to the reception tracks and mainline from Mandai Depot.


S1-S2 removal with concurrent backfilling works at Sembawang Airbase C&C

Saturday, 17 June 2017

TEL1 Tunnelling Completes

Bored tunnelling works have completed this month under Stage 1 of the project between Woodlands North, Mandai Depot and the Sembawang Airbase cut and cover tunnel site. 12 tunnel drives were launched using 3 Earth Pressure Balance machine 4 Slurry TBMs which bore through the weathered Bukit Timah Granite to complete the 8km network of mainline and reception tunnels beneath Woodlands.

For most of the tunnels, the basic structural completion (BSC) have already been achieved with the first stage concreting (FSC) for the track bed, together with brackets installation for the various SWC. Trackworks are slated to commence through the tunnels by the end of 2017, with the remaining SWCs gaining access from the 2nd half of 2018.


Mandai Depot Stabling Yard

Sunday, 7 May 2017

May Tunnel Progress

Tunnelling works for Stage 1 of the line will be completed by next month with the final 100m long Woodlands bound tunnel being driven between LS2 and Woodlands South station. Concurrently, the twin TBMs from Springleaf will breakthrough at the RTS Facility Building, completing the longest mainline drives (2km) under the TEL project.


TEL 1&2 Tunnel Chart, May 2017
T206: Completed Changi Bound tunnel between LS2 and WDS under the second drive of TBM 4

Wednesday, 1 March 2017

Mandai Depot - TBM 3 Second Breakthrough

Tunnelling works for the T206 project are wrapping up with 8 of the 10 bored tunnels completed. Cross passage excavation and the first stage concreting works are taking place within the tunnels. Structural, fittings and trackworks are progressing at the depot.


Stabling Yard nearing structural completion

Friday, 9 December 2016

Mandai Depot - Trackwork Begins

Commencement of the line's largest system-wide contract, led by CTCI for the design, supply, construction, testing and commissioning of trackwork and third rail system, took place this quarter with the staging ground prepared at the Mandai Depot. This is the second back-to-back trackwork project awarded to the Taiwanese contractor, with a smooth transition of resources expected from the recently completed Downtown Line 3.


Structure for the stabling yard, bus parking deck and perimeter wall mostly completed

Saturday, 5 November 2016

November Tunnel Progress

Tunnelling works for the line have been ongoing for 15 months now. 11 bored tunnels have been completed.


TEL1/2 Tunnel Chart, November 2016
T202 - Breakthrough of TBM 2 at Woodlands Station on October 10. This is the first contract to complete all bored tunnel excavation

Monday, 5 September 2016

S-893 Reassembly

Having completed the Changi Bound tunnel from LS2 to Woodlands, the re-assembly of S-893 (TBM 1) is taking place at LS1 for the RT3 tunnel drive to Woodlands Station. The TBM is expected to launch next month and breakthrough by mid-2017. TBM 3 has been retrieved from Mandai Depot and is held at the surface of LS2, awaiting to be reassembled for the Changi bound tunnel drive to Woodlands South Station.


Launch Shaft 1/ ES1

Saturday, 30 July 2016

July Tunnel Progress

Tunnelling works are underway along all the projects along stages 1 and 2 of the line, with the first slurry TBM for the T211 project launched at Bright Hill this week. 5 bored tunnels have been completed by the first half of the year and a further 5-8 tunnels are envisaged to complete by year end.

TEL1/2 Tunnel Chart, July 2016
T206 - Launch preparations for the second drive of TBM 4 for reception tunnel 1 at Sembawang Airbase C&C (Photo credits: LTA)

Sunday, 5 June 2016

Mandai Depot - TBM 3 Breakthroughs

The first Earth Pressure Balance TBM for the line broke through the retrieval point north of Mandai Depot last Saturday, completing the reception tunnel 3 drive from the launch shaft 1 (LS1). This is the fifth bored tunnel to be lined for the line, and is also the shallowest breakthrough point in the MRT construction history due to the unique utilization of TBMs for the construction of the reception tunnels leading to an at-grade depot.

Retrieval of the machine is underway for the subsequent tunnel drives from LS2 to Woodlands South station. Herrenknecht slurry machine S-893, together with TBM 5 for the Changi Bound drive from LS2 to Woodlands station and SBAB to Woodlands South station have completed similarly.


Lowering and installation of cradle for the retrieval of TBM 3 at Mandai Depot

Friday, 4 March 2016

Mandai Depot & T206 (III)

All 5 TBMs for the project have been launched and are excavating the mainline and reception tunnels. The single-span replacement POB along Woodlands Avenue 2 was launched on February 5. The old bridge will be demolished and have its piles removed ahead of the relaunch of TBM S-893 for the RT3 drive at the end of the year.


Replacement POB in construction along Avenue 2

Thursday, 21 January 2016

January Tunnel Progress

TEL1/2 Tunnel Chart, January 2016
(T206 - Reception tunnels emerge between the mainline tunnels in actuality, however shown otherwise on the chart for simple illustration)

Contract T202
Excavation of the Changi-bound tunnel is advancing at a slow pace and 2 cutterhead interventions have been performed since the launch of the TBM back in December. It's sister TBM is slated to commence mining on the Woodlands-bound tunnel by the end of this month.

Changi Bound Tunnel, T202 WDN-WDL (Dec 28)

Sunday, 6 December 2015

Mandai Depot & T206 (II)

Tunnelling works on the mainline tunnels between LS2 and WDL are progressing well. S-893 has successfully completed the 3-week long installation of the backup gantries during the transition from the initial to main drive, and has now advanced over 70 rings. S-894 has advanced 11 rings from the launch shaft. A gantry crane has been installed over the ES1/LS1 prior to the lowering of the EPB TBM last month. The backup gantries site beneath the portal crane over the shaft, while the machine is being assembled beneath.

The entire SBAB C&C structure has reached the formation level and casting works are underway to cast the base slab. The second of STEC'S EPB pre-assembled machine has been delivered to the launch shaft and will likely commence the first drive along the reception tunnels judging from the soil investigation and preparatory works along the reception tunnel route.

The T206 team recently celebrated their 2 million accident free man-hours.


Portal crane and backup gantries in preparations of tunnelling works at LS1

Monday, 23 November 2015

November Tunnel Progress

TEL 1/2 Tunnel Chart, November 2015

Contract T206
The first Earth Pressure Balance TBM for the Thomson-East Coast Line was lowered down into the Launch Shaft 1 last night. Manufactured by STEC, the EPB machine has commenced assembly works within the launch shaft and will do its first drive along the Reception Tunnel 3 (RT3) towards Mandai Depot. Tunnelling works should commence in January 2016.

Ring progress as of November 16,
S-893 - Changi Bound Tunnel: Ring 58 (9% completed) - Transitioning to main drive & installation of backup gantries
S-894 - Woodlands Bound Tunnel: Ring 11 (2% completed)

Ring progress as of November 29,
S-893 - Changi Bound Tunnel: Ring 70 (12% completed) - Transitioning to main drive & installation of backup gantries
S-894 - Woodlands Bound Tunnel: Ring 11 (2% completed)

Hoisting of the front shield (Nov 22) - Photo Cr: Ramalingam Rama

Sunday, 25 October 2015

October Tunnel Progress

TEL1/2 Tunnel Chart, October 2015

Contract T206
Excavation of the Changi Bound tunnel by S-893 commenced at the LS2 last month. 15 rings have been erected as of October 12, and 54 rings built as of October 25 (9% completed, ~ 3 rings/day). At the present advance rate, the estimated breakthrough for S-893 is slated around June 2016.

S-894 will commence excavation on the Woodlands Bound tunnel soon.

The T206 project utilizes the steel fibre reinforced concrete (SFRC) segments, a special type of tunnel lining which uses less steel, however is more durable and crack resistant. The segments were previously trialed on the C933 Downtown Line project and the LTA has extended the use of these segments along a 10km stretch of tunnels under the T206 & T207 projects of the Thomson-East Coast Line. The SFRC lining consists of 7+1 segments instead of the usual 5+1. The tunnel lining segments for T206 are currently being supplied by Kimlun in Malaysia.


Progress of S-893 on the Changi Bound tunnel between LS2 to Woodlands (October 24)

Saturday, 26 September 2015

Haze Contingency Measures

In light of the recent deterioration of the haze conditions across the country, preventive actions have been stepped up to protect the welfare and safety of the workers exposed to the hazardous outdoor conditions. The T206 Launch Shaft site was visited by the media yesterday afternoon to find out more about the numerous precautionary measures that have been implemented at the site.



Friday, 4 September 2015

Mandai Depot & T206

Excavation works progresses along the cut and cover structures along the T206 project.

Launch Shaft 1 & 2
The Changi Bound TBM has completed assembly works within the adit tunnel of LS2 and will launch by the middle of this month. Excavation of LS1 has completed and the team is now blasting the horizontal section on both ends for the adit tunnel. The depot-bound STEC EPBM is slated to commence tunnelling along RT3 by the end of the year.

SBAB C&C & Escape Shaft 2
The ES2 structure now has the entire S1 layer shored along its entire length. The north launch shafts at the Sembawang Airbase C&C tunnel has now been excavated down about 20 meters, close to the formation level with an approximate reduced level of 95.000. The gantry cranes have been installed around the launch shafts, and tunnelling here should commence by year end with the TBMs arriving and assembling in the 4th quarter.

Mandai Depot
Columns along the north end of the stabling area are currently being cast. The structure will feature 45 parallel tracks, more than thrice the width that of the Downtown Line's Gali Batu Depot. Each track will accommodate for 2 x 4 passenger cars to effectively house the entire fleet of the 43km Thomson-East Coast line. The depot has been intentionally over-designed for future fleet expansions should the need arises.


Mandai Depot, T201

Friday, 7 August 2015

August Tunnel Progress

Project T208
The second NFM TBM for the project was lowered down into the launch shaft on July 24, with assembly works almost completed. The delay in commencement of tunnelling works from the first machine were due to irregularities within the electrical system of the TBM which do not meet the local authority requirements.

The electrical system has been reworked around the end of July and mining works for TBM 1 should commence by this month.

Project T206
The second Herrenknecht mixshield S-894 was lowered down the LS2 on August 4. It's sister machine S-893 is similarly expected to commence tunnelling works by this month.

4 TBMs for the Thomson Line have been lowered down into their respective launch shafts thus far.


TEL1/2 Tunnel Chart, 7 August 2015