Friday, 30 September 2016

Great World Cast

Construction of the roof slab is taking place and is midway completed at the Great World station. Excavation works have commenced at the north end of the station, as well as the subway to River Valley road.


T220 Great World site

Excavation of entrance B and subway


North launch shaft

Excavation of station box



Waterproofing works to roof slab
Excavation pit

Excavation and shoring works for construction of the last zone roof slab
Tubular struts are installed for the first time in 30 years since the construction of the North South Line, and will be widespread-used in the upcoming projects along the east coast stretch of the line

South launch shaft/entrance A excavation and RC works



Excavation works at Great World City entrance