TEL1/2 Tunnel Chart, October 2015 |
Contract T206
Excavation of the Changi Bound tunnel by S-893 commenced at the LS2 last month. 15 rings have been erected as of October 12, and 54 rings built as of October 25 (9% completed, ~ 3 rings/day). At the present advance rate, the estimated breakthrough for S-893 is slated around June 2016.
S-894 will commence excavation on the Woodlands Bound tunnel soon.
The T206 project utilizes the steel fibre reinforced concrete (SFRC) segments, a special type of tunnel lining which uses less steel, however is more durable and crack resistant. The segments were previously trialed on the C933 Downtown Line project and the LTA has extended the use of these segments along a 10km stretch of tunnels under the T206 & T207 projects of the Thomson-East Coast Line. The SFRC lining consists of 7+1 segments instead of the usual 5+1. The tunnel lining segments for T206 are currently being supplied by Kimlun in Malaysia.