Friday, 30 March 2018

Orchard Cast (VI)

Structural works for the station, entrance and ventilation structures progresses at the site, with A&A works commencing at the North South Line and ION substructures. Backfilling and site clearing works are taking place around the cut and cover tunnel site in preparations for the SWC staging ground.


Orchard Station

Tuesday, 19 December 2017

Orchard Cast (V)

RC works are in progress at entrance B & bored pile works are in progress at entrance C.


Orchard Station

Sunday, 1 October 2017

Orchard Cast (IV)

The concourse and platform slabs of the station have been completed, and works on the lowest platform link level which will connect to the NSL station are in progress. Excavation works have completed at entrance B, and the roof structure of the cripple siding tunnel is mostly completed. Bored tunnel works from the 2nd drive are 75% completed with completion due next month, and the Stage 7 TD for the final stretch of underpass bored piling & excavation works to entrance C beneath Paterson Road is being prepared for implementation in the next quarter.





Orchard Station & Cripple Siding C&C tunnel site

Sunday, 9 July 2017

Orchard Excavation (II)

Excavation works are in progress at entrance B and the cut and cover tunnel. The second phase of bored piling works beneath Paterson Road is underway for the underpass construction to entrance C.


Next phase of traffic diversion along Paterson Road implemented for the subway bored pile construction to Wheelock

Wednesday, 12 April 2017

Orchard Cast (III)

Excavation and casting of the permanent structure continues.


Station site

Thursday, 22 December 2016

Orchard Excavation

Excavation and casting work continues at the Orchard site.


Bulk excavation works in full swing at the cut and cover tunnel

Thursday, 29 September 2016

Orchard Cast (II)

D-walling works for the project have been fully completed at the cut and cover tunnel ahead of schedule and excavation works have commenced there. Basement casting of the concourse slab is taking place at the station box. A major traffic realignment is being prepared at the Orchard/Paterson intersection for the underpass works.


Completed roof slab at Orchard station

Saturday, 18 June 2016

Orchard Cast

The diaphragm wall works for the station box are about completed and are progressing in full swing along the cut and cover tunnel. The roof slab for the station continues to be poured in stages. A second traffic diversion along Orchard Boulevard has been implemented for the construction of the underground linkway.


Excavation to the reduced level of the roof slab for rebar installation and casting

Saturday, 9 April 2016

Orchard D-walls (V)

D-walling works continue and progresses southwards along the cut and cover tunnel, while excavation works and casting of the roof slab for the top down construction of the station box takes place. Excavation of the launch shaft is ongoing.


Construction of the diaphragm wall for the cut and cover tunnel adjacent to the Orchard station box

Saturday, 26 December 2015

Orchard D-walls (IV)

A part of the Overseas Family School has completed demolishment works and earthworks and installation of bentonite silos are being done in preparations for the commencement of the diaphragm wall construction. Special care will be taken during the construction to minimize the movement of the existing NSL bored tunnels which come inches in proximity to the proposed cut and cover tunnel.

Casting works are being carried out for the slab over the launch shaft and northern section of the station box, which will employ a top-down construction method. The diaphragm wall construction continues at the southern end of the station box.


Demolishment of OFS for the construction of the cut and cover tunnel

Saturday, 3 October 2015

Orchard D-walls (III)

The first traffic diversion for T219 was implemented along Orchard Boulevard last month. The realigned road makes way for the construction of the shaft which will oversee the box jacking construction of the linkways between the existing NSL and the new station.

The 2 international schools have moved out by the start of the 3rd quarter, and preparations for the demolishment works have commenced for the future cut and cover tunnel site. The diaphragm wall of the TBM launch shaft seems to have been completed and excavation works should commence by year end.


T219 Orchard Station

Thursday, 16 July 2015

Orchard D-walls (II)

Diaphragm wall works have commenced at ION Orchard.


Site clearing at ION. A low level d-wall cutter by Bachy Soletanche is executing the excavation of the d-wall panel

Sunday, 5 April 2015

Orchard D-walls

Earth retaining structural works for the new Orchard Station have just commenced this week. 3 machines for the D-walling are currently on the site. 2 grabs are now excavating the D-wall for the launch shaft as well as part of the station. Behind them, a hydraulic cutter is on standby to take over and excavate the rocks that will be encountered in the panel closer to the formation level.

A single Herrenknecht slurry TBM (S-963) will be launched from the shaft and execute 2 drives towards Orchard Boulevard to complete both bored tunnels. Load tests are being carried out across the station footprint, while SI and site clearing works have started in front of ION Residences.


D-walling of the launch shaft (extreme left of the picture)

Friday, 16 January 2015

Orchard Earthworks

The Orchard station is currently the final site along the Thomson Line project to be executing earthworks due to its hilly terrain. Majority of the trees that are required to be felled have already done so, and hoardings around the site have gone up prominently along Orchard Boulevard and Paterson Road. The site office has been constructed at the junction of Orchard Boulevard and Grange Road, opposite Scape.

Herrenknecht will be supplying a Slurry TBM under T219 for the dual drives to Orchard Boulevard station. This is an alteration to the initial proposal of an EPB machine, probably due to the mixed ground conditions along the tunnel route. CSM Bessac, a subsidiary of main contractor Bachy Soletanche will facilitate in operating the tunnelling works.


The Overseas Family School will operate its Paterson campus until the end of Q2 this year before moving to its new campus at Pasir Ris
Earthworks at T219 Orchard Station

Monday, 29 September 2014

Orchard - Before the Trees Fell

Contract T219 is for the construction of Orchard Station, cripple sidings and twin bored tunnels towards Orchard Boulevard. Similar to T218, the site of the contract sits on a land currently occupied by the Overseas Family School (OFS). A new campus is currently being built at Pasir Ris, and OFS is expected to move out of the Paterson campus by the middle of next year.

Orchard Station
The new station will see 4 new entry points. This includes Wheelock Place, Paterson Road and Orchard Boulevard. A new Pedestrian Overhead Bridge will connect across the Paterson Road entrance as an additional entry point too. The existing entrance B along the North South Line station will be altered and integrated into a primary entrance for the Thomson Line. The station will have 3 main basements - A concourse (same level as B1 in Ion), platform (Ion B2) and transfer level (Ion B4), and will be constructed top-down using the diaphragm wall method.


Location of 3 of the new entrances to be built around the Paterson junction
Transfer to North South Line
A simplified layout of the interchange:

B1 - TSL Concourse/ ION B1
B2 - TSL Platform/NSL Concourse/ ION B2
B3 - NSL Platform
B4 - Transfer level

As the ground level at Orchard Boulevard is higher, the AMSL level for the Thomson Line Concourse and Platform will be higher than that of the NSL. From the Thomson Line, 2 pairs of escalators on each ends of the platform will bring you down to the transfer level. (B2 to B4) From the North South Line, 2 new pairs of escalators at Doors 3 and 10 of the southbound platform will be constructed to bring you to to the transfer level (B3 to B4). For barrier free linkage, the existing NSL concourse-platform lift will be extended one level down to the transfer level (B2 to B4). A pair of travellators will be installed across the span of the transfer.

The NSL station will undergo intensive A&A works and underpinning, which will prove to be challenging without disrupting the operational status of the existing busy station.

Future subway and paid link to go beneath the existing Orchard Boulevard
Bored Tunnelling
A launch shaft will be built north of the station (near the Paterson junction) for the drive of an EPB TBM to Orchard Boulevard. The existing POB along Orchard Boulevard near Wheelock will be demolished so as to extract the piles in the way of the tunnelling route. A new POB will be constructed to replace the existing bridge. There will be 1 cross passage between ORC-OBV.

C&C Tunnels and TSA
A cripple siding will extend the cut and cover portion of the site south of the station all the way to Grange Road. This will be an extensive site being one of the temporary staging areas (TSA) for trackwork. The overall site will also be shared with various system wide contractors (SWCs).

Future C&C cripple siding tunnel and TSA site

Friday, 25 July 2014

Final Contract Awards

Today, LTA released the finalized contract awards for the last 3 stations on the Thomson Line. With this, all civil works contracts have been closed and awarded, along with the contract for trackworks, T250.

The contract for T219 which is for the construction of Orchard station and associated tunnels has been awarded to a joint venture between Penta-Ocean Construction and Bachy Solentanche. Both companies have been involved in the construction of Singapore's MRT network. Penta-Ocean is currently working on Bendemeer station along Downtown Line Stage 3 (DTL3) while Bachy Solentanche was involved in the construction of Telok Ayer and Bugis stations on Downtown Line Stage 1 (DTL1). Worth noting is that Penta-Ocean has been the only contractor to bag a contract in each stage of the Thomson Line (TSL).

A view of the exit along Orchard Boulevard
Concourse level view of Orchard interchange station
Entrance along Paterson Road view

Contract T227 is for the construction of Marina South station and associated tunnels. This contract was awarded to a joint venture between Sinohydro Corporation and Sembcorp Design and Construction. As with Napier station, this is Sinohydro's first foray into the Singapore MRT construction market.

Concourse level view of Marina South station
A platform view of Marina South station
Looking down a new road at Entrances A and B

The final contract, T228, is for the construction of Gardens By The Bay station (current terminus of the TSL) and associated tunnels (including tunnels across the Marina Channel, ending in Gardens by the Bay - Bay East). This has been awarded to a joint venture of Nishimatsu Construction and Bachy Solentanche. Nishimatsu Construction is currently involved in the construction of mainline tunnels between Kaki Bukit and Ubi stations on the DTL3 as well as reception tunnels from the Tai Seng Facility Building to Ubi and Bedok North stations.


Concourse level at Entrance C
Entrance C

Contract T250 is for the trackworks along the entire TSL. This has been awarded to CTCI Corporation.

Thursday, 10 July 2014

Package C Renders

 A/E Consultancy services for package C of the Thomson Line were awarded to Aecom and SAA back in 2010. Effectively known as Civil Team 3 as construction works gear up, the design boundaries span from Whitley Road to Havelock. Stations included in this section are Stevens, Orchard Boulevard, Orchard, Great World and Havelock. Napier station is not included inside the design package as it is separately designed by the client.







Photos courtesy of SAA