Almost all vegetation have been cleared at the station site and ULS, with the center median hoarded up with concrete barriers while compact excavators remove the remaining obstructions beneath while canal diversion works take place.
Tunnelling to CDT is set to be a battleground between earth and infrastructure. A 500m section below Marymount Road will be bored parallel, directly below the existing Circle Line tunnels with 10-15m clearance, something that the local authorities have not endeavored before. Other challenges thrown into the works include tunnelling below the existing Macritchie Viaduct, Marymount Flyover, DTSS as well as concurrent projects like the North South Expressway and SPPG cable tunnel taking place simultaneously.
Tunnelling works at ULS are scheduled to commence by 2H 2015. ULS will have a cross passage integrated within the shaft. ULS-UTS will have a single CP, while ULS-CDT will feature 4 CPs within the tunnels.
|
Update Preview - Station box looking north |
|
Update Preview - Station box looking south |
|
Update Preview - Upper Thomson Launch Shaft (ULS) |