Tuesday, 13 March 2018

Mayflower Fit-Out

Backfilling and fitting works are in progress at the station. RC works for all entrances have completed to ground level, and RC works on the ventilation superstructures are in progress.


Mayflower Site

Sunday, 10 December 2017

Mayflower - Basic Structure Completion

The Mayflower Station has achieved the Basic Structure Completion (BSC) earlier this quarter, making it the first station along the entire line to do so. The T210 team accomplished this around 3 months ahead of schedule, an extremely remarkable feat in the MRT construction where most projects struggle to even meet the dateline.

Filling and reinstatement works are progressing over the roof slab as the RC works for the entrance and service superstructure takes place. Numerous road realignments will begin to take place around the site for the phased removal of the temporary steel road decking as part of the permanent works.


Several site visits have been facilitated for the various stakeholders surrounding the station following the milestone (Photo: SNGS Primary)

Tuesday, 12 September 2017

Mayflower Cast (V)

A realignment of Avenue 4 has been implemented for the RC construction of the 7th and final entrance B. The superstructure works for Entrance E & G are underway, and casting works for the closing of the station box are in progress to complete the station structure.


Realignment of Avenue 4

Wednesday, 28 June 2017

Mayflower Cast (IV)

Structural works for the station and entrances are largely completed. A realignment of Street 11 has taken place for the construction of the underpass link from the station to entrance D.


Basic structure completed at entrance D & realignment of AMK St 11 for the remaining subway construction

Tuesday, 7 March 2017

Mayflower Cast (III)

Basic structure of the entrances are progressively completing accompanied by backfilling works on the surface.


Entrance D backfill & casting of surface perimeter

Wednesday, 14 December 2016

Mayflower Cast (II)

Casting works for the station have reached the platform level where all excavation works have completed. The project is currently one of the quickest along the line, with the station and entrances seemingly on track to achieve basic structural completion next year - ahead of the indicative 2018 target.


Basement roof slab completed at Entrance D

Monday, 12 September 2016

Mayflower Cast

Casting of the concourse slab at the Mayflower station started in the previous quarter and and is largely completed at the subways and entrances. Excavation works are at the mezzanine level now.


T210 Mayflower Station

Saturday, 11 June 2016

Mayflower Excavation (III)

Bulk excavation together with the construction of the roof slab continues at Mayflower.


Thursday, 17 December 2015

Friday, 18 September 2015

Piling at Mayflower (V)

Piling works are entering its final phase at the Mayflower station. The stage 3B traffic diversion was implemented at the site last Saturday to make way for the construction of the remaining bored piles. The diversion will last until the end of the year.



Tuesday, 16 June 2015

Piling at Mayflower (IV)

Piling works at the Mayflower Station are now about 60% completed. The third traffic diversion along Avenue 4 was implemented earlier this month. The realigned road to the east now allow for piling to be done on the west side of the station box. The diversion is envisaged to last for 3 months. Grouting is taking place on the south side of the station as well.


Stage 3A Traffic Diversion

Tuesday, 17 March 2015

Piling at Mayflower (III)

SBP works have been on going for about 3 quarters now. A 3rd traffic diversion should take place around the middle of the year. 


Panorama of Mayflower Station, T210

Wednesday, 31 December 2014

Piling at Mayflower (II)

Bore piling works continue at the Mayflower site. A second traffic diversion was implemented mid-December at the junction of Street 11, swinging the twin carriageway of Avenue 4 towards the west. The diversion will last for 2-3 months. Instrumentation works have also begun with tiltmeters installed along the columns of the HDB flats surrounding the site.

Penta Ocean from the neighboring contract T211 is also preparing a small site south of Mayflower for preparatory works of the 2 TBMs that will be driven from Bright Hill, both of which will go beneath the foundations of Block 258. More will be shared in the T211 update.


December 24 - Panorama of Mayflower, T210
December 24 - Close up of traffic diversion 1A

Saturday, 13 September 2014

Piling at Mayflower

The groundbreaking ceremony for Mayflower station was commemorated along with Lentor last Saturday. At the Mayflower site, Avenue 4 has just been diverted last week to facilitate the construction of the bored piles for the retaining wall. The diversion will remain till end 2015, when the SBP construction is completed.

The ERSS of a station can be constructed using diaphragm walls as seen at Springleaf and Lentor. Another method of constructing the underground structures would be the use of secant bored piles (SBP). Over at Mayflower station, this method will be adopted.

Secant Bored Pile Construction
The pile's casing is first drilled into the ground, leaving 1-2m of the casing head exposed to the surface. The exposed cylinder guides the excavation of the bored pile, which is carried out next using a rotary drilling rig. The soil surrounding the borehole is supported by the casing. If the casing is not long enough to reach the required depth in the ground, bentonite slurry is used to support the soil below the casing. After excavation is complete, the reinforced steel cage is inserted into the casing, and concrete is poured. The casing is then removed and the retaining wall or ERSS is completed.


Mayflower Station
Diverted AMK Ave 4 at the junction with St 13
Groundbreaking Ceremony on September 6
Commencement of drilling for the secant bored pile

Tuesday, 3 June 2014

Making of Mayflower

Contract T210 is for the construction of the Mayflower station and was awarded to Hong Kong-based Gammon Construction, who have completed both the North East Line (NEL) and Downtown Line (DTL) Chinatown stations and the Bukit Panjang LRT previously. Mayflower station will see the most exits on any Thomson Line station with 7 exit structures being built. Situated on a slight incline, the station will see construction taking place in close proximity to many HDB blocks around. Already, a number of trees have been chopped down to make way for the station construction and will be re-planted once construction is done. Some walkways between the blocks will be demolished in the process as well.


A view of Ang Mo Kio Avenue 4 near the Kebun Baru CC on 4 May 2014

Looking down towards the main construction site.

A view of the existing tree cover on 4 May 2014.

Saturday, 1 March 2014

Works begin - Mayflower

Works have commenced at the site of Mayflower station with contractor for T210 - Gammon Construction - moving machinery on site. Currently, a test pile is being constructed and this marks the initial stage of construction ahead of further site clearing, construction of the earth retaining system and subsequent construction of the station superstructure. Gammon's site office has also been completed and works will begin in earnest soon.




A Gammon banner can be seen on the crane to the left.


Sunday, 9 February 2014

Mayflower to Lentor - Before the Trees Go

In this update we have a final glance at the dense vegetation that currently lines up AMK Avenue 4 where 2 main cut and cover structures would be built. Trees identified to be chopped for the construction are tied with red and white tape. This is also currently visible along Upper Thomson, in which we would do an update much later on. 

For the section between Mayflower and Lentor, agencies such as PUB and SP are still necessitating the various utility diversions works. These works are commanded with the use of mini excavators which can be seen lying near footpaths along the road. The trees should go within the next quarter.


Trees along Avenue 4 to clear for the future Mayflower Station

Scroll down for brief information on the related 2 contracts. More details will be updated when construction begins.

Sunday, 10 November 2013

Tunnel Chart for TSL

Here's the tunnel chart organised into two sheets - stage 1 and 2, and stage 3. The exact number for T206 is not known at the moment. A total of 36 TBMs (excluding T206) are set be procured for the entire TSL.

Disclosed Acronyms:
SBAB - Sembawang Airbase
TGR - Tagore
5XO - TS05 Crossover
ULS - Upper Thomson Launch Shaft





Saturday, 19 October 2013

Contract Award - T210, T203, T209 & T210

4 contracts have been awarded this month, on 18 October 2013. These consist of 3 stations and 1 contract to build the depot. Of the 3 stations, 1 contract is a build-only contract while the remaining 2 contracts involve design work in addition to construction. The contract awards are as follows:

T201 - Mandai Depot - Jurong Primewide
T203 - Woodlands station - GS Engineering & Construction
T209 - Lentor station - China Railway No. 5 Engineering
T210 - Mayflower station - Gammon Construction


An interior view of the paid transfer from the NSL platform at Woodlands

A new exit to be built at Woodlands

To date 7 contracts for TSL1 & TSL2 have been awarded. The remaining three include T213 (Caldecott - Samsung C&T), T206 (Tunnels between Woodlands station & Woodlands Ave 12 - Shanghai Tunnel) & T205 (Woodlands South - Woh Hup).