Saturday, 10 March 2018

Springleaf Backfill

Filling and compaction works are taking place over the completed structure of the station. Construction of the permanent utilities and carriageway of Upper Thomson Road are concurrently taking place in preparations for the Stage 3 traffic realignment scheme. Construction of entrance B2 has started.


Springleaf Station
Roof slab backfilled leading to the ventilation structure

Entrance C RC superstructure works


Temporary lane reduction and excavation & strutting works for the construction of escalator pits at entrance B2

Entrance B1 & B2
Entrance A2

Compaction and filling works across the site
Construction of curb along the permanent northbound carriageway
Launch shaft backfilled

Divider demolishment along the temporary road