A realignment of Avenue 4 has been implemented for the RC construction of the 7th and final entrance B. The superstructure works for Entrance E & G are underway, and casting works for the closing of the station box are in progress to complete the station structure.
Realignment of Avenue 4 |
Entrance D & C |
Entrance D |
Entrance C |
Realignment of Avenue 4 for Entrance B construction |
Removal of road decking for construction of Entrance B |
Realignment of Avenue 4 |
Entrance G structure casting to ground level |
Staircase for Entrance G |
Vent shaft 2 & cooling tower at Entrance G |
Casting of openings in the station structure |
Entrance E RC works to ground level |
Vent shaft 1 construction at Entrance E |
Hacking of secant bored piles |
Subway A/F site awaiting reinstatement as backfilling works are underway |
Entrance F |
Staircase constructed |
Entrance A |
Flood stairwell barrier cast |
Station overview |