Structure of the station is at varying progress with the basement roof and concourse slab cast at different zones. With the bored piling and ground improvement works completed, a total of 3 telescopic clamshell excavators are now facilitatating the excavation works for the top-down construction of the station.
| Upper Thomson Station |
| Entrance B site |
| Backfilling works taking place after the completion of the pipe jacking for the linkway |
| Excavation works around entrance A |
| Casting works completed at the basement roof and concourse levels |
| Excavation works to platform level |
| Excavation of station box |
| Excavation to concourse level |
| Commencement of excavation works around entrance D |
| Entrance D site |
| Entrance C site |