Saturday 9 September 2017

Tagore Backfill (II)

The Tagore site has begun demobilization works by the T208 team as it prepares to handover the site to CTCI and other SWCs for the temporary staging area works between Tagore and Mount Pleasant. The STP and gantry cranes have been demobilized, with hardcore compacted above the station box. The FSC, cross passage and bracket installation works are ongoing for the twin tunnels towards Springleaf.


Tagore C&C site
Gantry crane dismantled & hardcore filled above the roof slab
SWC portal access over the Woodlands bound tunnel
Northern section of the site will be backfilled slightly later due to the differential progress of the bored tunnelling works

STP dismantled at the site. Other storage areas on site are being cleared.

No comments:

Post a Comment

Note: only a member of this blog may post a comment.