Saturday, 18 June 2016

Orchard Cast

The diaphragm wall works for the station box are about completed and are progressing in full swing along the cut and cover tunnel. The roof slab for the station continues to be poured in stages. A second traffic diversion along Orchard Boulevard has been implemented for the construction of the underground linkway.


Excavation to the reduced level of the roof slab for rebar installation and casting










Lowering of backup gantries for the TBM

D-wall works along the cut and cover tunnel








No comments:

Post a Comment

Note: only a member of this blog may post a comment.