Sunday 1 October 2017

Orchard Cast (IV)

The concourse and platform slabs of the station have been completed, and works on the lowest platform link level which will connect to the NSL station are in progress. Excavation works have completed at entrance B, and the roof structure of the cripple siding tunnel is mostly completed. Bored tunnel works from the 2nd drive are 75% completed with completion due next month, and the Stage 7 TD for the final stretch of underpass bored piling & excavation works to entrance C beneath Paterson Road is being prepared for implementation in the next quarter.





Orchard Station & Cripple Siding C&C tunnel site
Dismantling of center divider along Paterson Road in preparation for the next traffic diversion (Stage 7) to be implemented next quarter
Excavation works for subway to Wheelock

Underpass structure cast
Underpinning works to NSL at entrance E
Underpass overview
Commencement of excavation works under pipe roof for linkway beneath Orchard Boulevard from station to ION (Photo: Thawon)
Excavation of the linkway featuring SCL along the vertical side walls and micro TBM-bored steel pipe roofing (Photo: Thomas Friedl)
Station box
Woodlands bound tunnel due to complete next month

Completion of excavation works at entrance B

Station box



Concourse level
KOP at the cripple siding interface
C&C tunnel site


Completed tunnel structure