Sunday, 21 September 2014

Mount Pleasant Earthworks

At Mount Pleasant, KTC has been subcontracted to facilitate the demolishment of the old police academy blocks. Works started since our previous update in June and the site had just recently been fully cleared. Earthworks are now underway to flatten the land before works on the retaining wall fully begin. 2 piling rigs and silos have been set up west of the site.


Overview of Mount Pleasant


The station would mainly serve CJC and the neighbouring residents within Chancery Hill, across the PIE
Twin tube tunnels will be bored down to the Thomson Cripple Siding (TCS), beside the MSF building. Caldecott can be distinctively seen.

August 18



Site photos taken by Tze Chai

No comments:

Post a Comment

Note: only a member of this blog may post a comment.