KTC which was subcontracted for earthworks at the Mount Pleasant site has since moved out and its site office has been demolished. Piling works have commenced at both the north and south launch shafts, with a priority of the completion of the south shaft first - which will subsequently be handed over to Daewoo of the neighbouring contract T216. The 3-storey site office for the LTA has been structurally completed south of the site and is in the process of being fitted out.
Under T215, Herrenknecht will be supplying a slurry TBM and STP for the tunnel drives from the north shaft to the TCS at Caldecott.
Fitting out of the T215 Site Office |
Intensified piling works at the south launch shaft |