Thursday, 1 February 2018

February Tunnel Progress

The T215 and T217 projects have successfully completed all tunnelling works this week with the docking of the 2 Herrenknecht Mixshield TBMs at the Caldecott cripple siding tunnel and Napier station respectively. 14 bored tunnel drives remain - bulk of which would be completed in the second quarter of the year.

The next breakthrough will take place at Caldecott by TBM 3 under the T212 project around end Feb/early March. Its sister TBM 2 will subsequently arrive approximately 6 weeks later, concluding the tunnelling works for Stage 2 and TELC2 in April.


TEL1/2 Tunnel Chart (January 2018)
TEL3 Tunnel Chart (February 2018)
Completion of TBM1 and the overall tunnelling works at T209 early January (Photo: Balakrishnan/CR5)
Docking of S-930 at Napier (Changi bound) and completion of overall T217 bored tunnel works (Jan 31) (Photo: Adelin)
Docking of S-936 at the Caldecott cripple siding tunnel (Woodlands bound drive) and completion of T215 bored tunnel works (February 5) (Photo:Tadashi Noto)

No comments:

Post a Comment

Note: only a member of this blog may post a comment.