Structural works for the station box are largely completed at the roof level and BSC is targeted by the end of the year. Casting of the north crossover tunnel is ongoing.
T202 Site overview |
Overrun tunnel structure |
North crossover tunnel |
Plan view |
External wall of station (East facade) |
Station box - North end falsework at concourse level service rooms for casting to roof level |
Entrance D and casting of wall at GL5 separating public and service area |
Cross section of station box with completed roof slab from GL7-16 |
Entrance C, external wall and roof slab construction from GL16 |
Rebar works for roof slab casting works at GL17-21 above south end of concourse public area |
Completed structure of the station to roof level (GL7-24) |
South crossover tunnel filling |
Site overview |
Launch shaft & Woodlands St 91 |