Sunday 3 December 2017

Woodlands South Cast (III)

Casting works for the station are now progressing along the internal RC partition and skinwall at the platform and concourse levels up to the roof structure.


Removal of S1 strut & basement roof - ground structure emerging at entrance A


Entrance B roof slab cast




Entrance D RC works from concourse to roof level
Internal partition wall construction around the south tunnel ventilation fan room at the concourse

Roof slab rebar installation along the UPN to Woodlands Health Campus

No comments:

Post a Comment

Note: only a member of this blog may post a comment.