Friday, 4 March 2016

Mandai Depot & T206 (III)

All 5 TBMs for the project have been launched and are excavating the mainline and reception tunnels. The single-span replacement POB along Woodlands Avenue 2 was launched on February 5. The old bridge will be demolished and have its piles removed ahead of the relaunch of TBM S-893 for the RT3 drive at the end of the year.


Replacement POB in construction along Avenue 2
The new bridge has a simply supported beam without an intermediate support for the reception tunnel to go through

Construction of the foundation of the stair landing
LS1 & LS2



TBM3 slowly advancing from the launch shaft in its initial drive (positioned under the blue umbrella to the right)
Batching plant created along Drive 17 to support the ground improvement works



ES2




SBAB

TBM4

Mandai Depot
Commencement of excavation at the reception portal for RT1,2 and 3

Superstructures for the substation and workshops are forming at the depot

Stabling yard

No comments:

Post a Comment

Note: only a member of this blog may post a comment.