Structure of the station has reached the underplatform level. Excavation of the linkways and initial drive of the Woodlands bound TBM towards Havelock are in progress.
| T222 Outram Park site |
| Replacement shields for TBM 2 over the Changi bound side |
| Initial drive of TBM |
| Bored piling works for new free area |
| New paid link between EWL and NEL concourse |
| EWL-NEL paid link |
| TSL-NEL paid link |
| Demobilization at south launch shaft |
| Retrieved backup gantries of TBM 2 |
| Station excavation completed |
| Site overview |