Wednesday 27 September 2017

Napier Excavation (III)

The relaunch of TBM S-930 at the Napier launch shaft for the Changi bound tunnel drive towards Orchard Boulevard took place earlier this month on September 15. Excavation works are at the S6 layer at the deepest point and RC works for the station's underplatform structure should start by the end of the year.


T217 Napier Station (View towards Tanglin)
View towards Holland
TBM segment and backup gantries supporting the initial drive

Initial drive commenced on Sep 15
Excavation works at station



Excavation works at entrance A and station






CP site
Adit works at the completed lower tunnel