Concourse slab of the station structure has been cast and excavation works are progressing down to the platform.
| Excavation works of UPC to the future Woodlands Health Campus |
| Concourse slab completed adjacent to entrance C which has completed excavation |
| Concourse slab cast |
| Possible road realignment along Avenue 1 over roof slab coming up for the construction of entrance D |
| Reinforcement works for concourse slab in Q1 prior to casting (Photo: LTA) |
| Excavation progressing down to platform level |
| Entrance A structure progressing up |
| Construction of service rooms and ventilation shaft at entrance A from concourse to roof level |
| Entrance B |