Piling works for the launch shafts and cut and cover tunnels have completed and the team is preparing for the commencement of excavation. Sin Ming Walk was realigned last month to facilitate the remaining SBP works along the station box. Piling works have also commenced on entrances C and D at the front facade of block 402 and 403.
A secondary storage site has been created beside the site office along the Bishan-AMK park, where 1 of the 4 Kawasaki TBMs for the project have been delivered.
Completed SBP at the north C&C tunnel, casting of capping beam and S1 installation works in preparation for excavation |
Casting of excavation pit wall |
North launch shafts & c&c tunnel stub |
Installation of struts |
Realignment of Sin Ming Walk in November for the station box piling works |
Piling works commences at entrance C |
Piling works commences at entrance D |
Capping beam casting for the south launch shafts |
Entrance B |