Thursday, 29 June 2017

Bright Hill Excavation (II)

Excavation works at the station box are ongoing to the platform level, with the concourse slab completed. The Woodlands bound tunnel to Mayflower has presumably been completed by TBM 4, and the remaining 3 TBMs are anticipated to complete by the next quarter.


Ground improvement works at the extracted H-pile foundation of the former POB along Upper Thomson Road
The replacement POB uniquely utilizes the existing staircase of the former bridge
Bored tunnelling works to Upper Thomson are almost completed, with TBM 2 along Thomson Plaza



Entrance B







Entrance C




TBM 3 tunnelling works
Tunnelling works for TBM 4 presumably completed with the absence of tunnel rings at the shaft surface