D-walling works continue at the Upper Thomson site. Piling works have completed at the Upper Thomson Launch Shaft (ULS) by the end of May and shoring/excavation works have commenced. Tunnelling works are scheduled to commence at the ULS by December this year.
May 13 - UTS site (cr: Bachy Soletanche Singapore) |
July 11 - Excavation at ULS |
June 18 |
June 18 |
June 18 |
June 18 |
July 3 |
Excavation at ULS |
Recharge wells installed near Shunfu Estate, across the road |