Sunday 4 January 2015

Upper Thomson D-walls & Piles

The station's ERSS will be constructed from north to south, with an implementation of a traffic diversion for each respective phase. The first traffic diversion has been scheduled within the next 2 months. King posts are being driven down along the former canal which will support the deck for the traffic diversion to come, while D-walling works have commenced at the entrance on the former site of the Thomson Post Office by Bachy Soletanche, subcontracted by Sato Kogyo.

Hirose has been subcontracted for shoring works under T212.

Upper Thomson Launch Shaft
As a kind gesture, the project team decided to install 12m high acoustic barriers at ULS for the Shunfu residents despite the site being a reasonable distance away from the blocks. Due to the obstruction of view, our updates will now be viewed upfront from the Lakeview side.


D-walling works at Entrance C - Bachy Soletanche Singapore
Driving of king posts into the former canal

Bentonite Silos by BSS erected in a cluster of 20 behind the site - Bachy Soletanche Singapore
Overview of Upper Thomson Station
Site clearing along Entrance B

King Post Installation


King Post Joint
King posts works along the former canal
Pile Driving Analyzer test
Pile Driving Analyzer test
Road Decking works



Traffic Diversion 1 to be implemented within the next 2 months.
October 8 - Drive through along the site
October 8 - Drive through along the site
October 8 - Drive through along the site

Upper Thomson Launch Shaft


December 12 - Erection of acoustic barriers
December 12 - Erection of acoustic barriers
December 12 - Erection of acoustic barriers
December 12 - Erection of acoustic barriers

December 28
December 28
December 28
December 28
December 28
December 28