Wednesday, 17 December 2014

Piling at Woodlands (II)

Piling works continue on at the Woodlands site with the 6 Bauers. The rigs are now spread out around the station box away from the crossover tunnel during the initial drilling. The site is viewed from a different angle - Causeway Point in this update.

A road notice has been put up informing motorists of the impending traffic diversions at the junction of Avenue 2/5 for the construction of the crossover tunnel, and a completion only in Q4 2017 when the tunnel is expected to have been backfilled. The diversions however have not started.







Avenue 2/5 close up

No comments:

Post a Comment

Note: only a member of this blog may post a comment.