The third traffic diversion under T205 has been implemented over at Woodlands South this morning. This diversion shifts the existing southbound Avenue 1 closer to Christchurch Secondary, alongside the already-diverted northbound road which had been earlier implemented on Oct 6.
With both carriageways of Avenue 1 fully diverted, D-walling works for the north perimeter of the station will commence in full swing from now. A subsequent diversion of Avenue 1 to the north can be expected in 6 months for the d-walling works on the south perimeter. Upon completion of the ERSS we expect excavation works to begin by the first half of 2016.
![]() |
New southbound carriageway diverted to the left. The station box will be located beneath the former road. |
October 5 - Pre diversion for the northbound road |
October 5 - Pre diversion for the northbound road |
October 5 - Pre diversion for the northbound road |
October 5 - Pre diversion for the northbound road |
![]() |
October 8 - Diverted northbound road |
![]() |
November 9 (subsequent pictures below taken on the same day) - Diverted southbound road |
![]() |
New signalised junction with Drive 16 |
![]() |
Travelling along the northbound road |
![]() |
![]() |
![]() |
![]() |
Travelling along the southbound road |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |