Excavation works have reached the plantroom level and is progressing down to the upper platform level. Assembly of TBM 1 has completed and commencement of tunnelling works to Maxwell are slated to begin tomorrow.
![]() |
| Concourse slab completed at the station |
| LS3 with backup gantries connection on the surface |
| TBM 1 assembled up for the lower drive towards Maxwell |
![]() |
| Looking up from the launch shaft |
![]() |
| Final preparations for the commencement of the EPBM |
| TBM will encounter the abandoned piles of the former UIC building during its initial drive, before undercrossing the EWL tunnels after advancing approximately 100 rings |
| Excavation & RC works at the station |
| View of the partially completed permanent monsoon drain structure cutting across the station roof beneath the gantry crane |
![]() |
| Casting works for the plantroom level |
![]() |
![]() |
![]() |
![]() |
| Looking down from plantroom to Upper platform level |
![]() |
| Upper platform level RC slab works |
![]() |
| Sheet piling works for entrance C |
| Filling of temporary monsoon canal for the linkway construction and entrance B&C |
| LS4 handed over back to the T225 team earlier this month upon completion of the upper slab structure |
| Re-launch of TBM 2 on the Changi bound drive is slated by June |