Friday, 1 September 2017

Woodlands North Cast (V)

Structural works for the station box are largely completed at the roof level and BSC is targeted by the end of the year. Casting of the north crossover tunnel is ongoing.


T202 Site overview

Tuesday, 1 August 2017

August Tunnel Progress

The 2km long twin tunnels between Springleaf station and the RTS Facility Building have completed under the T207 project. These are the longest single mainline tunnel drives achieved under the MRT construction since the Circle Line 4 project a decade ago. TBM 2 brokethrough the facility building overnight (Jul 31), while TBM 1 completed the Woodlands bound tunnel on July 9.

Together with the completion of TBM C2 at Springleaf under the T208 project, bored tunnelling works are officially completed under the Civil Team 1 projects. With 4 TBM drives completed in July, 6 TBMs remain between 5XO and Caldecott station under Stage 2 of the line.

Envisaged completion for remaining 6 TBMs under TEL2:
T209 TBM 1/2 - Q4 2017
T211 TBM 1 - Sep 2017
T212 TBM 1 - Q4 2017
T212 TBM 2/3 - Q1 2018


TEL1/2 Tunnel Chart, July 2017
T207: TBM 1 breakthrough at Facility Building on July 9 (Photo: Raju)

Wednesday, 19 July 2017

Gardens By The Bay - TBM Reassembly

Tunnelling works for the Woodlands bound tunnel has completed from Gardens by the Bay station to the Marina East shaft, where the TBM has U-turned and commenced the second drive back towards the station. RC structure of the station is progressing between the platform and concourse levels.


Completed 700m long Woodlands bound tunnel beneath the Marina Channel