Monday 10 September 2018

Stevens - TBM 2 Completes

Excavation works for the Woodlands bound tunnel from Mount Pleasant to Stevens completed today with the docking of TBM 2 outside the d-wall of the station. The NFM slurry machine was launched in September 2016, having spent the last 2 years completing the 1.44km tunnel drive. The final month of tunnelling works proceeded cautiously between the stacked DTL tunnels, as well as beneath the Wayang Satu Flyover and Bukit Timah Canal.

Its sister machine is approximately 100m behind and is similarly scheduled to dock at the station next month.


TEL3 Tunnel Chart - September 2018
Docking of TBM 2 (left) at the D-wall of Stevens Station (Photo: Oop Pocca)

No comments:

Post a Comment

Note: only a member of this blog may post a comment.