Structure of the station has now progressed to the underplatform level of the Changi bound platform. Conversion to main drives are underway for both TBMs.
Shenton Way station |
TBM 1 beneath MC street (9% completed) |
Lowering of pipes for pipe jacking works at the EWL protection shaft |
4 of 6 50m-long pipes completed, will support the EWL tunnels from below as prior to the TBM passing |
LS3 |
Casting of UPN level above concourse |
Plantroom level |
Upper underplatform level cast |
Casting works at upper underplatform level along trackbed |
Transfer beam for concourse to lower platform escalators at the upper underplatform level |
Excavation works to the lower platform level |
TBM 1 20% completed, conversion to main drive underway |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.