Structure of the station has now progressed to the underplatform level of the Changi bound platform. Conversion to main drives are underway for both TBMs.
| Shenton Way station |
| TBM 1 beneath MC street (9% completed) |
![]() |
| Lowering of pipes for pipe jacking works at the EWL protection shaft |
![]() |
| 4 of 6 50m-long pipes completed, will support the EWL tunnels from below as prior to the TBM passing |
| LS3 |
![]() |
| Casting of UPN level above concourse |
![]() |
![]() |
| Plantroom level |
![]() |
| Upper underplatform level cast |
![]() |
| Casting works at upper underplatform level along trackbed |
![]() |
![]() |
| Transfer beam for concourse to lower platform escalators at the upper underplatform level |
![]() |
| Excavation works to the lower platform level |
![]() |
| TBM 1 20% completed, conversion to main drive underway |