Friday 21 April 2017

Gardens By The Bay Cast (II)

Casting of the permanent structure at the station is progressing at varying levels, with portions of the platform and tunnel walls along both bounds completed. The second phase of traffic realignment, to be implemented next month, will see Marina Gardens Drive reduced to a single lane dual carriageway.


Gardens By The Bay station site
TBM now undercrossing the Marina Channel at approximately 30m depth towards Marina East
TEL works at Gardens by the Bay East
GBME shaft with tunnel eye and TBM cradle being constructed ahead of the TBM arrival
[T302] Deep soil mixing activity has started by the neighbouring TELC5 project
[T302] D-walling activities for the future station structure
Entrance C dual elevator and triple escalator pits visible in the slab
Skin wall and concourse slab completed
RC works for basement roof level progressing
Rebar works for concourse level
Segment storage yard for TBM

Casting of underplatform level around GL19-25
Casting of underplatform level, escalator pits and tunnel wall around GL10-16
Platform slab and tunnel wall completed around GL4-10
Casting of tunnel roof at crossover interface (GL1-4)

No comments:

Post a Comment

Note: only a member of this blog may post a comment.